HomeMy WebLinkAbout7302RESOLUTION NO. 7302 A RESOLUTION AUTHORIZING THE REPAIR OF THE RAILROAD SPUR SERVICING THE DOANE PRODUCTS COMPANY AND APPROPRIATING FUNDS THEREFOR WHEREAS, a railroad spur servicing the Doane Products Company at the Air- port Industrial Park was constructed by the City's contractor in 1991 as part of the City's incentive package to the Company; and WHEREAS, the City's Director of Public Works has determined that the rail- road spur is in need of immediate repair due to settlement of portions of the track; and WHEREAS, the need for the repair is related to the design and construction of the railroad spur rather than routine maintenance; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, COLORADO, that: CPrTTNN1 1 Part 1 of the proposal submitted by United Railroad Services Company to the City in the attached letter dated January 5, 1994, is hereby accepted. CFrTTnN 9 The Purchasing Agent be, and he is hereby authorized to execute a purchase order authorizing said work to be completed. SECTION 3. Funds for said repair work, estimated to be approximately $15,000, shall be transferred from Projects to be Determined, Account No. 034 - 1994 - 100 -0 -40 -2264, to, and all expenditures charged to Account No. 034 -1994- 100 - 000 - 040 -8820. ATTEST: City Cler INTRODUCED January 24 ,1994 B CHARLES JONES Councilperson APPROVED: esi ent of the Council -2- JAN 05 '94 11:21 AM Page - SERVICES CO. January 5, 1994 City of Pueblo 211 E. "D" Street Pueblo, CO 81003 Attn- Mike Beyer We would like to present the following proposals for repairs to the spur track serving Doane Products Inc. 1) Remove approximately 150' section of track over culvert and approximately 40' section of track around derail. Grade area to allow for approximately 8 " -10" of ballast. Existing ballast will be either disposed over bank or mixed in with subgrade. The subgrade will be compacted by wheel rolling with a backhoe. Lay stabilization fabric and reinstall track using new ballast. We estimate approximately 4 -5 days to complete all work for a price of $9950. This work can be completed during the week of January 10 -14, and would require the track to be out of service for approximately 3-4 days. Replacement of ties, if required, would be an additional charge. 2) Undercut approximately 1200' of track. Lay stabilization fabric. Reballast and surface track. The undercutter will cut approximately 8" to 9" from beneath ties. In order to achieve the 12" ballast section desired we would have to change the elevation of the track and have run offs on either end. We estimate approximately 5 working days to complete all work at a price of $29,500. We can begin mobilizing the week of Jan. 10 -14 and complete the work and demobilize the week of Jan. 17 -21. The track would have to be out of service while we performed the work. If you have any questions please do not hesitate to contact our office. Sincerely, Steven R. Graves General Manager SRG /prc 3151 NOME STREET - AURORA, COLORADO - 80010 303 - 344 -5649 - FAX 303 - 341 -5950