RESOLUTION NO.16275
A RESOLUTION RATIFYING AN EMERGENCY CONSTRUCTION
CONTRACT IN THE AMOUNT OF $224,305.40 WITH PARKER
EXCAVATING, INC., FOR EMERGENCY SANITARY SEWER
POINT REPAIR AT 2609 SPRUCE ST., PROJECT NO. 24-033
(WWAN03) AND APPROVING THE PURCHASING AGENT'S
EXECUTION OF THE SAME
WHEREAS, an emergency sanitary sewer repair was authorized by the Mayor in
accordance with Section 1-10-5 of the Pueblo Municipal Code; and
WHEREAS, the point repair work was awarded to Parker Excavating, Inc., under the
2024-2026 multi -year point repair contract; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that
SECTION 1 _
City Council ratifies and approves the contract for repair of the sanitary sewers at 2609
Spruce St. with Parker Excavating, Inc., Project No. 24-033 (WWAN03) — Emergency Point
Repair awarded to said bidder in the amount of $224,305.40.
SECTION 2.
Funds for Project 24-033 (WWAN03) — Emergency Point Repair shall be from the Sewer
User Fund.
SECTION 3.
The Purchasing Agent was authorized to execute said contract on behalf of Pueblo, a
Colorado Municipal Corporation, and the City Clerk properly affixed the seal of the City thereto
and attested the same.
SECTION 4.
The officers and staff of the City are authorized to perform any and all acts consistent with
the intent of this Resolution and the contract to implement the transactions described therein.
Furthermore, all actions previously taken by officers and staff of the City consistent with the
contract, including contract change order in the amount of $15,344.90 and any other payment
authorized under the contract are hereby ratified.
Docusign Envelope ID: 6D86F154-1749-44EE-B8E7-A48A34FD3397
SECTION 5.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED: March 23, 2026
Signed by:
ATTESTED BY: � Pt _
aF�e�ee�
DEPUTY CITY CLERK
BY: Brett Boston
MEMBER OF CITY COUNCIL
ocuSigned by:
APPROVED:
PRESIDE COUNCIL
Docusign Envelope ID: 6D86F154-1749-44EE-B8E7-A48A34FD3397
City Clerk's Office Item # M1
of
1111--PUEBLO
colDorado
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: March 23, 2026
TO: President Mark Aliff and Members of City Council
CC: Mayor Heather Graham
VIA: Vince Petkosek, Deputy City Clerk
FROM: Andra Ahrens, Director Wastewater
SUBJECT: A RESOLUTION RATIFYING AN EMERGENCY CONSTRUCTION
CONTRACT IN THE AMOUNT OF $224,305.40 WITH PARKER
EXCAVATING, INC., FOR EMERGENCY SANITARY SEWER POINT
REPAIR AT 2609 SPRUCE ST., PROJECT NO. 24-033 (WWAN03) AND
APPROVING THE PURCHASING AGENT'S EXECUTION OF THE SAME
SUMMARY:
This Resolution ratifies and approves award of a construction contract to Parker
Excavating, Inc., for emergency sanitary sewer point repairs at 2609 Spruce St.
PREVIOUS COUNCIL ACTION:
None
BACKGROUND:
On October 1, 2025, the property owner of 2609 Spruce St. has notified the Wastewater
Department that they were having sewer backup issue in their service line. They also
reported a sinkhole in the alley. A television crew was sent out to inspect the main and
they discovered multiple sags ranging from 50% to 100% and medium joint offsets in the
sewer main. They couldn't televise the whole main from either end due to the sags.
These defects will further deteriorate the pipe, increase the chance of collapse and
immediate backup in the main. To fix these defects as well as the sinkhole, an emergency
repair was performed to remove and replace the whole main.
The repair work was performed under the Sanitary Sewer Point Repair multi -year
contract under which two contractors were qualified via competitive bid. An estimate was
prepared, and Parker Excavating was the lowest bidder and accepted the work.
The cost breakdown for the project is as follows:
Docusign Envelope ID: 6D86F154-1749-44EE-B8E7-A48A34FD3397
Sanitary Sewer Replacement -related
Total: $ 97,334.65 70%
Surface Improvement Related
Total: $ 126,970.75 30%
Grand Total: $ 224,305.40 100%
FINANCIAL IMPLICATIONS:
Funding for this project came from the sanitary sewer rehabilitation budget funded by the
Sewer User Fund. Funding was available and had been budgeted, appropriated, and
allocated to Project No. 24-033 (VVVVAN03) — Emergency Point Repair.
BOARD/COMMISSION RECOMMENDATION:
Not applicable
STAKEHOLDER PROCESS:
None
ALTERNATIVES:
Not approve the Resolution would require a finding that there was not an emergency
condition.
RECOMMENDATION:
Approval of the Resolution.
ATTACHMENTS:
1. 03-23-26 2609 Spruce St Emergency Point Repair Attachment
2024-2026 Emergency Sanitary Sewer Point Repair
2609 Spruce St
Date 1012312025
Miller Pipeline, LLC
Parker Excavating, Inc.
Project Number: 24-033 (WWAN03)
Item
Description
Estimated
1
Remove and Replace 8" PVC Less than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
430
$ 64,500.00
$ 48,590.00
2
Remove and Replace 8" PVC More than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
3
Remove and Replace 10" PVC Less than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
4
Remove and Replace 10" PVC More than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
5
Remove and Replace 12" PVC Less than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
6
Remove and Replace 12" PVC More than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
7
Remove and Replace 15" PVC Less than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
8
Remove and Replace 15" PVC More than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
9
Remove and Replace 4" Service Tap Less than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
10
Remove and Replace 4" Service Tap More than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
11
Remove and Replace 6" Service Tap Less than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
12
Remove and Replace 6" Service Tap More than 10' Deep
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
13
P pe Asphalt Patch -4" HMA on 4" Class 6 ABC For 8" and 10"
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
1420
$ 120, 700.00
$ 106, 500.00
14
P pe Asphalt Patch -5" HMA on 6" Class 6 ABC For 8" and 10"
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
15
A p alt Patch -4" HMA on 4" Class 6 ABC For 12" and 15"
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
16
A p alt Patch -5" HMA on 6" Class 6 ABC For 12" and 15"
1-20
LF
$ -
$ -
21-100
LF
$ -
$ -
>100
LF
$ -
$ -
17
Remove and Replace 7" Reinforced Concrete
1-20
SF
$ -
$ -
21-100
SF
$ -
$ -
>100
SF
1530
$ 27,540.00
$ 28,305.00
18
Remove and Replace 6" Reinforced Concrete
1-20
SF
$ -
$ -
21-100
SF
$ -
$ -
>100
SF
$ -
$ -
19
Remove and Replace 4" Concrete
1-20
SF
$ -
$ -
21-100
SF
$ -
$ -
>100
SF
$ -
$ -
20
Remove and Replace Standard Curb and Gutter
1-20
LF
$ -
$ -
21-100
LF
47
$ 2,397.00
$ 2,326.50
>100
LF
$ -
$ -
21
Install or Remove and Replace 6" Curb Head
1-20
LF
$ -
$ -
21 -1 00
LF
$ -
$ -
>100
LF
$ -
$ -
22
Install Extra Lean Concrete (FlowFill)
1-20
CY
10
$ 1,950.00
$ 1,640.00
21-100
CY
$ -
$ -
>100
CY
$ -
$ -
23
Class 6 Base Course for Gravel Surfaced Alleys
TN
230
$ 9,200.00
$ 7,590.00
24
Remove Camera/Cleaning Head/Tap Cutter
HR
$ -
$ -
25
Remove and Replace 48" Diameter Manhole
with 1 Invert
EA
$ -
$ -
with 2 Inverts
EA
1
$ 6,500.00
$ 5,300.00
with 3 Inverts
EA
$ -
$ -
with 4 Inverts
EA
$ -
$ -
26
Remove and Replace 60" Diameter Manhole
with 1 Invert
EA
$ -
$ -
with 2 Inverts
EA
$ -
$ -
with 3 Inverts
EA
$
$
with 4 Inverts
EA
$ -
$ -
27
Calcium Aluminate Coat 48 -inch Manhole
1-10
VF
$ -
$ -
11-15
VF
$ -
$ -
>15
VF
$ -
$ -
28
Calcium Aluminate Coat 60 -inch Manhole
1-10
VF
$ -
$ -
11-15
VF
$ -
$ -
>15
VF
$ -
$ -
29
Rebuild Manhole Bench and Trough 48 -inch Manhole
LS
$ -
$ -
30
Rebuild Manhole Bench and Trough 60 -inch Manhole
LS
$ -
$ -
31
Reinstate Services - 4"
EA
18
$ 6,300.00
$ 6,984.00
32
Reinstate Services - 6"
EA
$ -
$ -
33
Mobilization
LS
1
$ 1,750.00
$ 1,725.00
Total $ 240,837.00 $ 208,960.50
With Contingency $ 289,004.40 $ 250,752.60
CONTRACT CHANGE ORDER
CITY OF PUEBLO DEPARTMENT OF PUBLIC WORKS
Project Number: 24-033 (WWAN03) Change Order No. : ONE 3/3/2026
Project Name : 2024, 2025 and 2026 Sanitary Sewer Point Repair
2609 Spruce St
Contractor: PARKER EXCAVATING INC.
1428 Stockyard Rd., Pueblo, CO 81001
You are hereby requested to comply with the following changes from the plans & specifications:
Bid Item
Description of Changes
Decrease
Increase
No.
Contract By
Contract B
1
REMOVE & REPLACE 8" PVC PIPE <10' DEEP (>100LF)
($678.00)
2
ASPHALT PATCH - 4" HMA ON 4" CLASS 6 ABC FOR 8" AND 10" PIPE
($5,006.25)
3
REMOVE & REPLACE 7" REINFORCED CONCRETE (>100SF)
($3,848.00)
4
REMOVE & REPLACE STANDARD CURB AND GUTTER (21-100LF)
($2,326.50)
5
INSTALL EXTRA LEAN CONCRETE (FLOWFILL) (>100CY)
$4,592.00
6
CLASS 6 BASE COURSE FOR GRAVEL SURFACED ALLEYS
($7,590.00)
8
REINSTATE SERVICES - 4"
($1,164.00)
10
REMOVE & REPLACE STANDARD CURB AND GUTTER (1-20LF)
$1,020.00
11
REMOVE AND REPLACE 48" DIAMETER MANHOLE (WITH 4 INVERTS)
$7,380.00
12
CHANGE ORDER - SERVICE REPAIR BY KNM DUE TO THE DEFECTIVE MAIN
$7,676.25
13
TRAFFIC CONTROL
$8,525.40
14
PAYMENT AND PERFORMANCE BONDS
($20,612.75)II
$6,764.00
$35,957.65
TOTAL (Decrease) /Increase
Net Adjustment This Change Order $
15,344.90
Amount of Previous Change Order(s) $
0.00
Original Contract Amount $
208,960.50
Total Adjusted Contract Amount To Date $
224,305.40
Reason For Change: Actual Field Quantities.
The time provided for completion of the contract is changed by 0 calendar days.
This document shall become an amendment to the contract and all provisions of the contract apply hereto.
Prepared by: Date:
Wastewater Civil Engineer
Reviewed by: Date:
Wastewater Engineering Manager
Accepted by: Date:
Contractor's Representative
If this Change Order causes an increase from the original contract price, signed approval by the Director
constitutes representation that lawful appropriations are sufficient to cover such increase.
Approved by: Date:
Director of Wastewater
FORM CO100.1299
Page 1 of 1
24-033 (WWAN03)
2024 -2026 Emergency Sanitary Point Repair
2609 Spruce St