City Clerk's Office Item # M4
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: October 27, 2025
TO: President Mark Aliff and Members of City Council
CC: Mayor Heather Graham
VIA: Marisa Stoller, City Clerk
FROM: Andra Ahrens, Director Wastewater
SUBJECT: A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $123,633.00 TO INDUSTRIAL CONSTRUCTORS /
MANAGERS, INC. AND SETTING FORTH $12,363.30 FOR
CONTINGENCIES AND ADDITIONAL WORK FOR PROJECT NO. 25-
073 (WWAN04) FY2025 WASTEWATER SECONDARY CLARIFIER #2
REHABILITATION AT THE JAMES R. DIIORIO WATER RECLAMATION
FACILITY AND AUTHORIZING THE PURCHASING AGENT TO
EXECUTE THE SAME.
SUMMARY:
This Resolution awards a construction contract to Industrial Constructors / Managers,
Inc. for Project No. 25-073 (WWAN04), FY2025 Wastewater Secondary Clarifier #2
Rehabilitation at the James R. DiIorio Water Reclamation Facility (WRF). The project will
replace the damaged AR plate.
PREVIOUS COUNCIL ACTION:
None
BACKGROUND:
The WRF treats all the wastewater for the City of Pueblo, and the Secondary Clarifier is
the final step in the separation of the solids from the water. The plate in the secondary
clarifier is worn out and is causing issues with the seals. The suction manifold will need
to be replaced due to the age and lack of suction it is producing. The scum trough will
need to be repaired due to the ware of the arms that rub while going under the trough
and which has almost rubbed completely through the trough. Without this rehabilitation,
it puts the facility at risk not to have a backup in case of an outage of another clarifier.
To protect the public interest, this secondary clarifier requires rehabilitation. Specifically,
this project will consist of removing the old suction manifold, scum trough and removing
the old wear plate from the bottom of the clarifier, installing a new wear plate, grouting
the wear plate, installing the suction manifold, installing the refurbished scum trough and
installing new manifold gaskets and seals.
FINANCIAL IMPLICATIONS:
The cost of the construction project was bid at $123,633.00 with contingencies of
$12,363.30 Funds are available from the Sewer User Funds and appropriated to Project
No. 25-073 (WWAN04).
BOARD/COMMISSION RECOMMENDATION:
Not applicable
STAKEHOLDER PROCESS:
None
ALTERNATIVES:
If no rehabilitation is performed on the secondary clarifier, the condition of the secondary
clarifier will continue to deteriorate until an emergency repair is required. The Water
Reclamation Facility would also risk violating its discharge permit if a secondary clarifier
outage were to happen.
RECOMMENDATION:
Approval of the Resolution.
ATTACHMENTS:
1. 10-27-25 2nd Clarifier bid tabulations
2. 10-27-25 Secondary Clarifier site map
RESOLUTION NO. 16152
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN
THE AMOUNT OF $123,633.00 TO INDUSTRIAL
CONSTRUCTORS / MANAGERS, INC. AND SETTING FORTH
$12,363.30 FOR CONTINGENCIES AND ADDITIONAL WORK
FOR PROJECT NO. 25-073 (WWAN04) FY2025 WASTEWATER
SECONDARY CLARIFIER #2 REHABILITATION AT THE JAMES
R. DIIORIO WATER RECLAMATION FACILITY AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE
SAME.
WHEREAS, competitive bids for Project No. 25-073 (WWAN04) FY2025 Wastewater
Secondary Clarifier #2 Rehabilitation at the James R. DiIorio Water Reclamation Facility have
been received and examined; and
WHEREAS, the proposal of Industrial Constructors / Managers, Inc. of Pueblo, Colorado
was the lowest of those bids determined to be responsive; NOW, THEREFORE
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that
SECTION 1.
The City Council authorizes Project No. 25-073 (WWAN04) FY2025 Wastewater
Secondary Clarifier #2 Rehabilitation at the James R. DiIorio Water Reclamation Facility to be
performed, and the contract for said project is hereby awarded to Industrial Constructors /
Managers, Inc., in the amount of $123,633.30.
SECTION 2.
Funds for Project 25-073 (WWAN04) shall be from the Sewer User Funds.
SECTION 3.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
A Colorado Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and
attest the same.
SECTION 4.
In addition to the amount of the bid set forth, as aforementioned, an additional amount as
stipulated in this section is hereby established for contingencies and additional work.
SECTION 5.
The officers and staff of the City are directed and authorized to perform any and all acts
consistent with the intent of this Resolution and the contract to implement the transactions
described therein.
INTRODUCED: October 27, 2025
BY: Brett Boston
MEMBER OF CITY COUNCIL
APPROVED: __________________________
PRESIDENT OF CITY COUNCIL
ATTESTED BY: ________________________
CITY CLERK