HomeMy WebLinkAbout6126RESOLUTION NO. 6126
A RESOLUTION AUTHORIZING THE EXECUTION OF
A SUPPLEMENTAL AGREEMENT WITH LONCO, INC.,
FOR PROFESSIONAL SERVICES CONCERNING THE
SOUTH UNION AVENUE BRIDGE REHABILITATION
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, COLORADO, that:
SECTION 1.
A Supplemental Agreement between the City of Pueblo and
Lonco, Inc., the original of which is on file in the office of the
City Clerk and is made a part hereof by reference, for professional
services in performing engineering design and inspection services
for the rehabilitation of the South Union Avenue Bridge, for com-
pensation not to exceed $17,000.00, with such terms as the City
Manager may require, and upon approval as to form by the City At-
torney, be and hereby is authorized and approved.
SECTION 2.
The City Manager is hereby authorized to execute said
Agreement on behalf of the City of Pueblo, a Municipal Corporation,
and the City Clerk shall affix the seal of the City thereto and
attest the same.
SECTION 3.
Funds for said services shall be paid from Account Number
02- 1984 -100- 000 - 040 -2217.
INTRODUCED December 28 ,1987
By DOUGLAS L. RING
Councilman
APPROVED:
LF of the Council
ATTEST:
City Clerk
- 2 -
1987 BRIDGE REHABILITATION
PROGRAM FOR UNION AVENUE BRIDGE
SUPPLEMENTAL CONTRACT FOR CHANGE OF SCOPE OF SERVICE
THIS FIRST SUPPLEMENTAL CONTRACT, made this C12 ✓ day of
haw 190, by and between the City of'Pueblo, hereinafter referred
to as the City, and LONCO, INC., 2680 Eighteenth Street, Denver, CO 80211,
hereinafter referred to as the Engineers.
WHEREAS, authority exists in the Law and Funds have been budgeted,
appropriated and otherwise made available, and a sufficient unencumbered
balance thereof remains available for payment.
WHEREAS, required approval, clearance and coordination has been
accomplished from and with appropriate agencies; and
WHEREAS, the City and the Engineer have heretofore entered into a
contract dated September 22, 1986, hereinafter referred to as the basic
contract and made part hereof by reference, which provides for design
services for rehabilitation of the existing bridge on Union Avenue over the
Arkansas River and Railroad track in Pueblo, Colorado; and
WHEREAS, the parties hereto now desire to amend the basic contract with
respect to the revision in scope of work changing the type 3 barrier rail
originally proposed to a type more characteristic to the adjacent Historic
District consisting of a type 4 concrete barrier rail with brick set and also
the addition of new lighting for the bridge 'to again reflect the character of
the Historic District. These changes will be reflected in the Preliminary
Design, Final Design and Construction Observation and Administration. This
will effect Article 1, Section III, Paragraph 6, 7, & 9, for the completion of
this work; and
Page 1 of 3
, WHEREAS, these changes have substantially increased the effort on the part of
the Engineer to complete the work, it is therefore deemed by the City to be in
the best public interest to supplement the basic contract; and
NOW, THEREFORE, it is hereby agreed that:
A. The basic contract, unless specifically revised or amended herein,
shall be and remain in full force and effect with respect to the
contractual relationship between the parties hereto.
B. ARTICLE 1, Section III, Paragraph 6 and 7 add to the basic contract
the work of including a concrete barrier rail and new bridge
lighting to reflect the character of the adjacent Historical
District of Union Avenue to north.
C. ARTICLE 1, Section III, Paragraph 9 add to the basic contract
construction observation from the original estimate of 60 working
days to the proposed Construction Contract of 120 working days.
D. ARTICLE III, Section 1, amend the fees as follows:
1) Paragraph A delete the figure $26,000.00 and replace with the
figure $30,000.00
2) Paragraph B delete the figure $27,000.00 and replace with the
figure $40,000.00
3) Paragraph C delete the figure $53,000.00 and replace with the
figure $70,000.00
Page 2 of 3
IN WITNESS WHEREOF, the parties hereto have executed this contract the
day and year first above written.
APPROVED AS TO FORM:
By
City Attor
CITY OF PUEBLO:
resident of City Counc 1
ATTEST:
TC er
LONCO, INC. Consulting Engineer ATTEST:
By
Secretary
MV
IM 0 of`
YS
Agreements -8 ftKifiedmns Eng.
Page 3 of 3