HomeMy WebLinkAbout15778RESOLUTION NO. 15778 A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF $1,438,085 TO MILLER PIPELINE LLC AND SETTING FORTH $287,617 FOR CONTINGENCIES AND ADDITIONAL WORK FOR PROJECT NO. 24-114 (CI2113) SANITARY SEWER EXTENSION AT NORTHERN AVENUE PROJECT AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME WHEREAS, competitive bids for the Project No. 24-114 (CI2113) Sanitary Sewer Extension at Northen Avenue Project have been received and examined; and WHEREAS, the proposal of Miller Pipeline LLC of Pueblo, Colorado was the lowest of those bids determined to be responsive; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that SECTION 1. City Council authorizes Project No. 24-114 (CI2113) Sanitary Sewer Extension at Northern Avenue Project to be performed, and the contract for said project is hereby awarded to Miller Pipeline LLC, in the amount of $1,438,085. SECTION 2. Funds for Project 24-114 (CI2113) shall be from the ARPA Funds Infrastructure - Sewer North (Project Account CI2113). SECTION 3. The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo, A Colorado Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the same. SECTION 4. In addition to the amount of the bid set forth, as aforementioned, an additional amount as stipulated in this section is hereby established for contingencies and additional work. SECTION 5. The officers and staff of the City are authorized to perform any and all acts consistent with the intent of this Resolution and the contract to implement the transactions described therein. SECTION 6. This Resolution shall become effective immediately upon passage and approval. INTRODUCED: October 15, 2024 BY: Roger Gomez MEMBER OF CITY COUNCIL APPROVED: __________________________ PRESIDENT OF CITY COUNCIL ATTESTED BY: ________________________ DEPUTY CITY CLERK City Clerk's Office Item # M2 Background Paper for Proposed Resolution COUNCIL MEETING DATE: October 15, 2024 TO: President Mark Aliff and Members of City Council CC: Mayor Heather Graham VIA: Marisa Stoller, City Clerk FROM: Andrew Hayes, Public Works Director SUBJECT: A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF $1,438,085 TO MILLER PIPELINE LLC AND SETTING FORTH $287,617 FOR CONTINGENCIES AND ADDITIONAL WORK FOR PROJECT NO. 24-114 (CI2113) SANITARY SEWER EXTENSION AT NORTHERN AVENUE PROJECT AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME SUMMARY: Attached is a Resolution awarding a construction contract to Miller Pipeline LLC for Project No. 24-114 (CI2113) Sanitary Sewer Extension at Northern Avenue Project. The City of Pueblo continues to experience and plan for growth. PREVIOUS COUNCIL ACTION: On July 25, 2022, by Resolution No. 14948, City Council approved the expenditure of $2,000,000.00 in American Rescue Plan Act (ARPA) funds to be used for constructing sewer infrastructure. BACKGROUND: In general, this project will consist of installing approximately 2,500 linear feet of 21-inch diameter pipe and installing the manholes associated with the sewer main as well as surface improvement necessary to complete the project detailed in the plans and specifications. Sanitary sewer will be extended from the intersection of Surfwood Lane and Highway 78 (Northern Avenue) to Bandera Parkway. The total cost of the project is estimated at $1,725,702, including contingencies. FINANCIAL IMPLICATIONS: The cost of the construction project was bid at $1,438,085 with contingencies of $287,617. Funds are available and will be paid from Project CI2113, ARPA Funds Infrastructure Sewer North. BOARD/COMMISSION RECOMMENDATION: Not applicable to this Resolution. STAKEHOLDER PROCESS: None. ALTERNATIVES: Alternative No. 1: No Action - denial of this ordinance would cancel this project and deter future development. RECOMMENDATION: Approval of the Resolution. ATTACHMENTS: 1. 10-15-24 24-114 Sanitary Sewer Extension at Northern Avenue Project Attachment