HomeMy WebLinkAbout10791ORDINANCE NO. 10791
AN ORDINANCE TRANSFERRING $503,915.07 FROM WW9999
TO WWAN03, FOR PROJECT NO. 20-059 (WWAN03) 2021-
2023 SANITARY SEWER POINT REPAIR - 250 WILLIAM WHITE
BLVD PROJECT AND AUTHORIZING THE PURCHASING
AGENT TO EXECUTE THE SAME.
WHEREAS, the repair work was performed under the Sanitary Sewer Point Repair multi-
year contract under which three contractors were qualified via competitive bid. An estimate was
prepared, and Parker Excavating was the lowest bidder, but could not perform the work.
WHEREAS, Miller Pipeline, LLC (previously known as K.R. Swerdfeger Construction,
Inc) of Pueblo, Colorado was the next low bidder and accepted to perform Project No. 20-059
(WWAN03) 2021-2023 Sanitary Sewer Point Repair 250 William White Blvd; NOW,
THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
Funds in the amount of $503,915.07 are hereby transferred from account Project
WW9999 into account Project WWAN03, 2021-2023 Sanitary Sewer Point Repair 250 William
White Blvd Project, and budgeted and appropriated for project WWAN03.
SECTION 2.
City Council authorizes Project No. 20-059 (WWAN03) 2021-2023 Sanitary Sewer Point
Repair 250 William White Blvd Project, to be performed, and the contract for said project is
hereby awarded to said bidder in the amount of $503,915.07.
SECTION 3.
Funds in the amount of $503,915.07 will be paid from the Sewer User Funds for Project
No. 20-059 (WWAN03).
SECTION 4.
The Mayor is hereby authorized to execute said contract on behalf of Pueblo, a Colorado
Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 5.
The officers and staff of the City are directed and authorized to perform any and all acts
consistent with the intent of this Ordinance and the contract to implement the transactions
described therein.
SECTION 6.
This Ordinance shall become effective on the date of final action by the Mayor and City
Council.
Action by City Council:
Introduced and initial adoption of Ordinance by City Council on September 09, 2024.
Final adoption of Ordinance by City Council on September 23, 2024.
____________________________
President of City Council
Action by the Mayor:
Approved on _______________.
Disapproved on ______________ based on the following objections:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
____________________________
Mayor
Action by City Council After Disapproval by the Mayor:
Council did not act to override the Mayor's veto.
Ordinance re-adopted on a vote of ____________, on _____________
____________________________
President of City Council
ATTEST
________________________________
City Clerk
City Clerk's Office Item # R1
Background Paper for Proposed
Ordinance
COUNCIL MEETING DATE: September 23, 2024
TO: President Mark Aliff and Members of City Council
CC: Mayor Heather Graham
VIA: Marisa Stoller, City Clerk
FROM: Andra Ahrens, Director Wastewater
SUBJECT: AN ORDINANCE TRANSFERRING $503,915.07 FROM WW9999 TO
WWAN03, FOR PROJECT NO. 20-059 (WWAN03) 2021-2023
SANITARY SEWER POINT REPAIR - 250 WILLIAM WHITE BLVD
PROJECT AND AUTHORIZING THE PURCHASING AGENT TO
EXECUTE THE SAME.
SUMMARY:
Attached is an Ordinance transferring $503,915.07 from WW9999 to WWAN03 for
Project No. 20-059 (WWAN03) 2021-2023 Sanitary Sewer Point Repair - 250 William
White Blvd Project. This project repaired the broken force main pipe segment and
performed additional work required to protect public health and safety and the
environment on the north and south sides of Highway 96.
PREVIOUS COUNCIL ACTION:
None
BACKGROUND:
On March 27, 2024, the Wastewater Department discovered a leakage in the force
main near 250 William White Boulevard. After an extensive site investigation, the
Wastewater Department discovered wastewater ponding in swale along the east side of
the Holcim and Agra and on the north and south sides of Highway 96. In order to
protect public health and safety and the environment, an emergency repair was
necessary to repair the broken pipe segment, perform additional work required to
mitigate wastewater ponding in swale along the east side of the Holcim and Agra and
on north and south sides of Highway 96, remove and replace contaminated soil, place
erosion and sediment control, remove contaminated road base and import new material
and regrade swales to flow properly.
FINANCIAL IMPLICATIONS:
The funds in the amount of $503,915.07 are being transferred from Project WW9999 to
WWAN03.
The cost of the sanitary sewer emergency point repair was initially estimated at
$5,500.00, but due to the additional work performed, the final cost of the repair
amounted to $503,915.07. Funds are available and will be paid from the Sewer User
Funds which have been budgeted and appropriated to Project No. 20-059 (WWAN03).
BOARD/COMMISSION RECOMMENDATION:
Not applicable
STAKEHOLDER PROCESS:
None
ALTERNATIVES:
None
RECOMMENDATION:
Approval of the Ordinance
ATTACHMENTS:
1. 09-09-24 20-059 250 William White Blvd Emergency Point Repair Attachment