HomeMy WebLinkAbout15617RESOLUTION NO.15617
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT
IN THE AMOUNT OF $267,230.41 TO FINSTERWALD
LANDSCAPING AND IRRIGATION FOR PROJECT NO. 24-052,
CONCRETE IMPROVEMENTS - WEST 29TH STREET PHASE 1
(I-25 TO HIGH STREET), SETTING FORTH $82,769.59 FOR
CONTINGENCIES, AND AUTHORIZING THE PURCHASING
AGENT TO EXECUTE SAME
WHEREAS, competitive bids for Project No. 24-052, Concrete Improvements - West 29th
Street Phase 1 (I-25 to High Street) have been received and examined; AND,
WHEREAS, the proposal of Finsterwald Landscaping and Irrigation was the lowest bid
determined to be responsive, and the Committee of Awards recommends to the City Council
that it authorizes Project No. 24-052, Concrete Improvements - West 29th Street Phase 1 (I-25 to
High Street) to be performed; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that
SECTION 1.
The City Council authorizes Project No. 24-052, Concrete Improvements - West 29th
Street Phase 1 (I-25 to High Street) to be performed, and the contract for said project is hereby
awarded to Finsterwald Landscaping and Irrigation in the amount of $267,230.41.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of the City
of Pueblo, a Colorado Municipal Corporation, and the City Clerk shall affix the seal of the City
thereto and attest same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount
as stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional
SECTION 4.
Funds in the amount of $350,000.00, for the contract and contingencies, shall be from
Project Account HUAN01, Street Resurfacing.
SECTION 5.
The officers of the City of Pueblo are authorized to perform any and all acts consistent
with this Resolution to implement the policies and procedures described herein.
SECTION 6.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED: May 13, 2024
BY: Regina Maestri
MEMBER OF CITY COUNCIL
APPROVED: __________________________
PRESIDENT OF CITY COUNCIL
ATTESTED BY: ________________________
CITY CLERK
City Clerk's Office Item # M1
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: May 13, 2024
TO: President Mark Aliff and Members of City Council
CC: Mayor Heather Graham
VIA: Marisa Stoller, City Clerk
FROM: Andrew Hayes, Public Works Director
SUBJECT: A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $267,230.41 TO FINSTERWALD LANDSCAPING AND
IRRIGATION FOR PROJECT NO. 24-052, CONCRETE
IMPROVEMENTS - WEST 29TH STREET PHASE 1 (I-25 TO HIGH
STREET), SETTING FORTH $82,769.59 FOR CONTINGENCIES, AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE SAME
SUMMARY:
Attached is a resolution awarding a Construction Contract to Finsterwald Landscaping
and Irrigation for Project No. 24-052, Concrete Improvements - West 29th Street
Phase 1 (I-25 to High Street).
PREVIOUS COUNCIL ACTION:
None.
BACKGROUND:
This project will consist of ADA curb ramp and sidewalk improvements to West 29th
Street, from I-25 to High Street. This Resolution awards the construction contract to
Finsterwald Landscaping and Irrigation.
FINANCIAL IMPLICATIONS:
Funds in the amount of $350,000.00 (contract and contingencies) will be paid from
Project Account HUAN01, Street Resurfacing.
BOARD/COMMISSION RECOMMENDATION
None.
STAKEHOLDER PROCESS:
None.
ALTERNATIVES:
Denial of this resolution will cancel the project.
RECOMMENDATION:
Approval of the Resolution.
ATTACHMENTS:
1. 24-052 Bid Summary