HomeMy WebLinkAbout15516RESOLUTION NO. 15516
A RESOLUTION RATIFYING AN EMERGENCY
CONSTRUCTION CONTRACT IN THE AMOUNT OF $4,374.92
WITH PARKER EXCAVATING, INC. FOR EMERGENCY
SANITARY SEWER POINT REPAIR AT THE WASTEWATER
TREATMENT PLANT DRYING BED DRAIN LINE, PROJECT NO.
20-059 (WWAN03) AND APPROVING THE PURCHASING
AGENT’S EXECUTION OF THE SAME
WHEREAS, an emergency sanitary sewer repair was authorized by the Mayor in
accordance with Section 1-10-5 of the Colorado Pueblo Municipal Code; and
WHEREAS, the point repair work was awarded to Parker Excavating, Inc., under the
2021-2023 multi-year point repair contract; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that
SECTION 1.
City Council ratifies and approves the contract for repair of the sanitary sewers at the
Wastewater Treatment Plant Drying Bed Drain Line with Parker Excavating, Inc., Project No.
20-059 (WWAN03) awarded to said bidder in the amount of $4,374.92.
SECTION 2.
Funds for Project 20-059 (WWAN03) shall be from the Sewer User Fund
SECTION 3.
The Purchasing Agent was authorized to execute said contract on behalf of Pueblo, a
Colorado Municipal Corporation, and the City Clerk properly affixed the seal of the City thereto
and attested the same.
SECTION 4.
The officers and staff of the City are authorized to perform any and all acts consistent
with the intent of this Resolution and the contract to implement the transactions described
therein. Furthermore, all actions previously taken by officers and staff of the City consistent with
the contract, including any payments authorized under the contract, are hereby ratified.
SECTION 5.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED: February 26, 2024
BY: Dennis Flores
MEMBER OF CITY COUNCIL
APPROVED:
PRESIDENT OF CITY COUNCIL
ATTESTED BY:
CITY CLERK
City Clerk's Office Item # M14
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: February 26, 2024
TO: President Mark Aliff and Members of City Council
CC: Mayor Heather Graham
VIA: Marisa Stoller, City Clerk
FROM: Andra Ahrens, Director Wastewater
SUBJECT: A RESOLUTION RATIFYING AN EMERGENCY CONSTRUCTION
CONTRACT IN THE AMOUNT OF $4,374.92 WITH PARKER
EXCAVATING, INC. FOR EMERGENCY SANITARY SEWER POINT
REPAIR AT THE WASTEWATER TREATMENT PLANT DRYING BED
DRAIN LINE, PROJECT NO. 20-059 (WWAN03) AND APPROVING THE
PURCHASING AGENT’S EXECUTION OF THE SAME
SUMMARY:
This Resolution ratifies and approves the award of a construction contract to Parker
Excavating, Inc. for emergency sanitary sewer point repairs at the Wastewater
Treatment Plant Drying Bed Drain Line.
PREVIOUS COUNCIL ACTION:
None
BACKGROUND:
On September 1st, 2023, the Wastewater Treatment Plant reported that they had
backup issues in the drying bed drain line. A television crew was sent out to inspect the
drain line, but they could not televise to the end of the pipe segment due to debris in the
line. After the line was cleaned and televised again, they discovered a large joint offset
and an obstruction in the last segment of the pipe and could not make through the
entire line. An emergency repair was performed to fix the joint offset and remove the
obstacle, so the line would drain properly and not cause any backups.
The repair work was performed under the Sanitary Sewer Point Repair multi-year
contract under which three contractors were qualified via competitive bid. An estimate
was prepared, and Parker Excavating was the lowest bidder and accepted the work.
The cost breakdown for the project is as follows:
Sanitary Sewer Replacement-related
Total: $ 4,374.92 100%
Surface Improvement Related
Total: $ 0.00 0%
Grand Total: $ 4,374.92 100%
FINANCIAL IMPLICATIONS:
Funding for this project came from the sanitary sewer rehabilitation budget funded by
the Sewer User Fund. Funding was available and had been budgeted, appropriated,
and allocated to Project No. 20-059 (WWAN03).
BOARD/COMMISSION RECOMMENDATION:
Not applicable
STAKEHOLDER PROCESS:
None
ALTERNATIVES:
Not approve the Resolution, but this would require a finding that there was not an
emergency condition.
RECOMMENDATION:
Approval of the Resolution.
ATTACHMENTS:
1. 02-26-24 Wastewater Treatment Plant Drying Bed Drain Line Emergency Point
Repair Attachment