HomeMy WebLinkAbout15236RESOLUTION NO. 15236
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT
IN THE AMOUNT OF $157,181.50 TO BAHA CONSTRUCTION,
INC., FOR PROJECT NO. 23-010, CONCRETE
IMPROVEMENTS - NORTHERN AVENUE (PRAIRIE AVE TO I-
25) CDBG, SETTING FORTH $42,817.50 FOR
CONTINGENCIES, AND AUTHORIZING THE PURCHASING
AGENT TO EXECUTE SAME
WHEREAS, competitive bids for Project No. 23-010, Concrete Improvements - Northern
Avenue (Prairie Ave to I-25) CDBG have been received and examined; and,
WHEREAS, the proposal of Baha Construction, Inc., was the lowest of those bids
determined to be responsive, and the Committee of Awards recommends to the City Council
that it authorize Project No. 23-010, Concrete Improvements - Northern Avenue (Prairie Ave to I-25)
CDBG to be performed; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that
SECTION 1.
The City Council authorizes Project No. 23-010, Concrete Improvements - Northern
Avenue (Prairie Ave to I-25) CDBG, to be performed, and the contract for said project is hereby
awarded to Baha Construction, Inc., in the amount of $157,181.50.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of the City
of Pueblo, a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and
attest same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount
as stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work………$42,817.50
SECTION 4.
Funds for Project No. 23-010, in the amount of $199,999.00 (including contingencies
and additional work) shall be from Project CD2018, West 18th Street Expansion.
SECTION 5.
The officers of the City of Pueblo are authorized to perform any and all acts consistent
with this Resolution to implement the policies and procedures described herein.
SECTION 6.
The Resolution shall become effective immediately upon passage and approval.
INTRODUCED: May 8, 2023
BY: Vicente Martinez Ortega
MEMBER OF CITY COUNCIL
APPROVED: __________________________
PRESIDENT OF CITY COUNCIL
ATTESTED BY: ________________________
CITY CLERK
City Clerk's Office Item # T1
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: May 8, 2023
TO: President Heather Graham and Members of City Council
CC: Mayor Nicholas A. Gradisar
VIA: Marisa Stoller, City Clerk
FROM: Andrew Hayes, Public Works Director
SUBJECT: A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $157,181.50 TO BAHA CONSTRUCTION, INC., FOR
PROJECT NO. 23-010, CONCRETE IMPROVEMENTS - NORTHERN
AVENUE (PRAIRIE AVE TO I-25) CDBG, SETTING FORTH $42,817.50
FOR CONTINGENCIES, AND AUTHORIZING THE PURCHASING
AGENT TO EXECUTE SAME
SUMMARY:
Attached is a resolution awarding a Construction Contract to Baha Construction, Inc.,
for Project No. 23-010, Concrete Improvements - Northern Avenue (Prairie Ave to I-25)
CDBG
PREVIOUS COUNCIL ACTION:
None.
BACKGROUND:
This project will consist of ADA compliant concrete improvements along Northern
Avenue from South Prairie Avenue to the I-25 right-of-way. This Resolution awards the
construction contract to Baha Construction, Inc.
FINANCIAL IMPLICATIONS:
Funding in the amount of $157,181.50 plus $42,817.50 for contingencies will be paid
from Project CD2018 West 18th Street Expansion.
BOARD/COMMISSION RECOMMENDATION:
None.
STAKEHOLDER PROCESS:
None.
ALTERNATIVES:
Denial of this resolution will cancel this project.
RECOMMENDATION:
Approval of the Resolution.
ATTACHMENTS:
1. 23-010 Bid Summary