Loading...
HomeMy WebLinkAbout15236RESOLUTION NO. 15236 A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF $157,181.50 TO BAHA CONSTRUCTION, INC., FOR PROJECT NO. 23-010, CONCRETE IMPROVEMENTS - NORTHERN AVENUE (PRAIRIE AVE TO I- 25) CDBG, SETTING FORTH $42,817.50 FOR CONTINGENCIES, AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE SAME WHEREAS, competitive bids for Project No. 23-010, Concrete Improvements - Northern Avenue (Prairie Ave to I-25) CDBG have been received and examined; and, WHEREAS, the proposal of Baha Construction, Inc., was the lowest of those bids determined to be responsive, and the Committee of Awards recommends to the City Council that it authorize Project No. 23-010, Concrete Improvements - Northern Avenue (Prairie Ave to I-25) CDBG to be performed; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that SECTION 1. The City Council authorizes Project No. 23-010, Concrete Improvements - Northern Avenue (Prairie Ave to I-25) CDBG, to be performed, and the contract for said project is hereby awarded to Baha Construction, Inc., in the amount of $157,181.50. SECTION 2. The Purchasing Agent is hereby authorized to execute said contract on behalf of the City of Pueblo, a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest same. SECTION 3. In addition to the amount of the bid set forth, as aforementioned, an additional amount as stipulated in this section is hereby established for contingencies and additional work. Contingencies and Additional Work………$42,817.50 SECTION 4. Funds for Project No. 23-010, in the amount of $199,999.00 (including contingencies and additional work) shall be from Project CD2018, West 18th Street Expansion. SECTION 5. The officers of the City of Pueblo are authorized to perform any and all acts consistent with this Resolution to implement the policies and procedures described herein. SECTION 6. The Resolution shall become effective immediately upon passage and approval. INTRODUCED: May 8, 2023 BY: Vicente Martinez Ortega MEMBER OF CITY COUNCIL APPROVED: __________________________ PRESIDENT OF CITY COUNCIL ATTESTED BY: ________________________ CITY CLERK City Clerk's Office Item # T1 Background Paper for Proposed Resolution COUNCIL MEETING DATE: May 8, 2023 TO: President Heather Graham and Members of City Council CC: Mayor Nicholas A. Gradisar VIA: Marisa Stoller, City Clerk FROM: Andrew Hayes, Public Works Director SUBJECT: A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF $157,181.50 TO BAHA CONSTRUCTION, INC., FOR PROJECT NO. 23-010, CONCRETE IMPROVEMENTS - NORTHERN AVENUE (PRAIRIE AVE TO I-25) CDBG, SETTING FORTH $42,817.50 FOR CONTINGENCIES, AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE SAME SUMMARY: Attached is a resolution awarding a Construction Contract to Baha Construction, Inc., for Project No. 23-010, Concrete Improvements - Northern Avenue (Prairie Ave to I-25) CDBG PREVIOUS COUNCIL ACTION: None. BACKGROUND: This project will consist of ADA compliant concrete improvements along Northern Avenue from South Prairie Avenue to the I-25 right-of-way. This Resolution awards the construction contract to Baha Construction, Inc. FINANCIAL IMPLICATIONS: Funding in the amount of $157,181.50 plus $42,817.50 for contingencies will be paid from Project CD2018 West 18th Street Expansion. BOARD/COMMISSION RECOMMENDATION: None. STAKEHOLDER PROCESS: None. ALTERNATIVES: Denial of this resolution will cancel this project. RECOMMENDATION: Approval of the Resolution. ATTACHMENTS: 1. 23-010 Bid Summary