RESOLUTION NO. 14922
A RESOLUTION AWARDING A CONSTRUCTION
CONTRACT IN THE AMOUNT OF $227,017 TO DESCO
ACQUISITION LLC. DBA BLACKEAGLE ENERGY
SERVICES AND SETTING FORTH $22,701 FOR
CONTINGENCIES, FOR PROJECT NO. 22-029 (WWANO4)
FY2022 WATER RECLAMATION FACILITY EQUIPMENT
UPGRADE PROJECT AT THE JAMES R. DIIORIO WATER
RECLAMATION FACILITY AND AUTHORIZING THE
PURCHASING AGENT TO EXECUTE SAME
WHEREAS, competitive bids for the Project No. 22-029 (WWAN04) FY2022
Equipment Upgrade Project have been received and examined; and
WHEREAS, the proposal of Desco Acquisition LLC. dba Blackeagle Energy
Services, was the lowest of those bids determined to be responsive; NOW
THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
City Council authorizes Project 22-029 (WWAN04) FY2022 Equipment
Upgrade to be performed, and the contract for said project is hereby awarded to Desco
Acquisition LLC. dba Blackeagle Energy Services, in the amount of $227,017.
SECTION 2.
Funds for Project 22-029 (WWAN04) shall be from the Rehabilitation Funds.
SECTION 3.
The Purchasing Agent is hereby authorized to execute said contract on behalf of
Pueblo, A Municipal Corporation, and the City Clerk shall affix the seal of the City
thereto and attest the same.
SECTION 4.
In addition to the amount of the bid set forth, as aforementioned, an additional
amount as stipulated in this section is hereby established for contingencies and
additional work.
Contingencies and Additional Work………$22,701
SECTION 5.
The officers and staff of the City are authorized to perform any and all acts
consistent with the intent of this Resolution and the contract to implement the
transactions described therein.
SECTION 6.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED: June 27, 2022
BY: Vicente Martinez Ortega
MEMBER OF CITY COUNCIL
APPROVED:
PRESIDENT OF CITY COUNCIL
ATTESTED BY:
CITY CLERK
City Clerk’s Office Item # M-5
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: June 27, 2022
TO: President Heather Graham and Members of City Council
CC: Nicholas A. Gradisar, Mayor
VIA: Marisa Stoller, City Clerk
FROM: Andra Ahrens, Interim Director of Wastewater
SUBJECT: A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $227,017 TO DESCO ACQUISITION LLC. DBA
BLACKEAGLE ENERGY SERVICES AND SETTING FORTH $22,701
FOR CONTINGENCIES, FOR PROJECT NO. 22-029 (WWAN04) FY2022
WATER RECLAMATION FACILITY EQUIPMENT UPGRADE PROJECT
AT THE JAMES R. DIIORIO WATER RECLAMATION FACILITY AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE SAME
SUMMARY:
Attached is a Resolution awarding a construction contract to Desco Acquisition LLC. dba
Blackeagle Energy Service for Project No. 22-029 (WWAN04), FY2022. Remove and install
Gritt Classifier, Primary Grinder, Primary Sludge Pump, and (2) Primary Scum Pumps at the
James R. DiIorio Water Reclamation Facility.
PREVIOUS COUNCIL ACTION:
None
BACKGROUND:
The James R. DiIorio Water Reclamation Facility treats wastewater for the City of Pueblo. The
Gritt Classifier is no longer supported by the manufacturer and needs to be replaced with a
newer model. The Primary Grinder was removed from the Primary Clarifier and not replaced at
that time, the grinder chops up the debris before going into the digester, the Primary Grinder
needs to be installed to prevent formation of rags in the digester. The Primary Sludge Pump is
the back up to the main pumps and is currently undersized and needs to be replaced to be a
full-size backup. The Primary Scum Pumps removes the waste and debris from the Primary
Clarifier waste boxes and pumps it to the dissolved air floatation (DAF) building, the pumps are
not supported by the manufacturer. The Primary Scum Pumps are currently leaking, and no
parts are available to repair them. The Primary Scum Pumps need to be replaced to ensure the
waste is removed from the waste boxes.
FINANCIAL IMPLICATIONS:
The cost of the construction project was bid at $227,017 with contingencies of $22,701. Funds
are available from the Rehabilitation Funds and appropriated to Project No. 22-029 (WWAN04).
BOARD/COMMISSION RECOMMENDATION:
Not applicable
STAKEHOLDER PROCESS:
None
ALTERNATIVES:
Alternative No. 1 - No Action
If no upgrades are performed on the Gritt Classifier, Primary Grinder, Primary Sludge pump, and
Primary Scum Pumps the condition of the equipment would continue to deteriorate until an
emergency repair is required at a higher cost than a planned project. The James R. DiIorio
Water Reclamation Facility would also risk violating its discharge permit if the equipment
upgrades are not upgraded, and an outage were to happen.
RECOMMENDATION:
Approval of the Resolution.
Attachments:
Bid Summary Sheet