HomeMy WebLinkAbout14890RESOLUTION NO. 14890
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT
IN THE AMOUNT OF $413,343 TO K.R. SWERDFEGER
CONSTRUCTION, INC., AND SETTING FORTH $82,669 FOR
CONTINGENCIES, FOR PROJECT NO. 22-019 (WWAN05)
FY2022 MANHOLE REHABILITATION PROJECT AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE
SAME
WHEREAS, competitive bids for PROJECT NO. 22-019 (WWAN05), FY2022
Manhole Rehabilitation Project have been received and examined; and
WHEREAS, the proposal of K.R. Swerdfeger Construction, Inc. of Pueblo, Colorado
was the lowest of those bids determined to be responsible, and the Committee of Awards
recommends to the City Council that it authorize PROJECT NO. 22-019 (WWAN05) to be
performed; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
City Council authorizes PROJECT NO. 22-019 (WWAN05), FY2022 Manhole
Rehabilitation Project, to be performed, and the contract for said project is hereby awarded
to said bidder in the amount of $413,343.00.
SECTION 2.
Funds for PROJECT NO. 22-019 (WWAN05) shall be from Sewer User Funds.
SECTION 3.
The Purchasing Agent is hereby authorized to execute said contract on behalf of
Pueblo, a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto
and attest the same.
SECTION 4.
In addition to the amount of the bid set forth, as aforementioned, an additional
amount as stipulated in this section is hereby established for contingencies and additional
work.
Contingencies and Additional Work…………..$82,669.
SECTION 5.
The officers and staff of the City are and authorized to perform any and all acts
consistent with the intent of this Resolution and the contract to implement the transactions
described therein.
SECTION 6.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED May 23, 2022
BY: Vicente Martinez Ortega
MEMBER OF CITY COUNCIL
APPROVED:
PRESIDENT OF CITY COUNCIL
ATTESTED BY:
DEPUTY CITY CLERK
City Clerk’s Office Item # M-1
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: May 23, 2022
TO: President Heather Graham and Members of City Council
CC: Nicholas A. Gradisar, Mayor
VIA: Marisa Stoller, City Clerk
FROM: Andra Ahrens, Interim Director of Wastewater
SUBJECT: A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $413,343 TO K.R. SWERDFEGER CONSTRUCTION, INC.,
AND SETTING FORTH $82,669 FOR CONTINGENCIES, FOR PROJECT
NO. 22-019 (WWAN05) 2022 MANHOLE REHABILITATION PROJECT
AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE SAME
SUMMARY:
During routine maintenance on the sanitary mains by the collections crew, an evaluation
of the manholes is also performed to determine the severity of deterioration. The
manholes are ranked using the National Association of Sewer Service Companies
(NASSCO) evaluation criteria – the higher the ranking, the worse the deterioration.
Manholes for the 22-019 (WWAN05) FY2022 Manhole Rehabilitation Project had to
meet two requirements, be the highest ranking on the evaluation list and not already be
on a rehabilitation list for the sanitary main segment to be replaced. To protect the
public interest, these manholes require rehabilitation. Manholes will be rehabilitated by
rebuilding the wall thickness with a cementitious material and sealing with an epoxy
coating or, in more severe cases, being removed, replaced and epoxy coated.
PREVIOUS COUNCIL ACTION:
None
BACKGROUND:
During routine inspection of the sanitary mains, an evaluation of the manholes, manhole
benches and troughs are performed to determine the severity of deterioration in the
manhole structures and to prioritize them accordingly. The manholes chosen for the 22-
019 (WWAN05) FY2022 Manhole Rehabilitation Project had the highest ranking for
rehabilitation and the connected main was not on the Main Rehabilitation List.
The existing manholes will be rehabilitated with calcium aluminate and epoxy coating
and manhole benches and troughs will be rebuilt with fast-setting cementitious material
to maintain the intended function of the sewer system and secure a continuous service
to the public.
FINANCIAL IMPLICATIONS:
The cost of the construction project was bid at $413,343.00 with contingencies of
$82,669. Funds are available from the Sewer User Funds and have been budgeted and
appropriated to Project No. 22-019 (WWAN05).
BOARD/COMMISSION RECOMMENDATION:
Not applicable
STAKEHOLDER PROCESS:
None
ALTERNATIVES:
Alternative No. 1 – No Action
The Wastewater Department would take no action. The manholes would continue to
deteriorate until they eventually collapse warranting an emergency repair and possibly
endangering the public.
RECOMMENDATION:
Approval of the Resolution.