ORDINANCE NO. 9954
AN ORDINANCE APPROVING THE SECOND
AMENDMENT TO THE PROFESSIONAL ENGINEERING
SERVICES AGREEMENT BETWEEN THE CITY OF
PUEBLO, A COLORADO MUNICIPAL COPORATION, AND
NORTHSTAR ENGINEERING AND SURVEYING, INC.
RELATING TO THE DESIGN AND ENGINEERING OF THE
ARKANSAS RIVER FLOOD LEVEE MASTER PLANNING
AND DESIGN AND AUTHORIZING THE MAYOR TO
EXECUTE SAME
WHEREAS, NorthStar Engineering and Surveying was selected to provide
professional engineering services for the Arkansas River Levee Park Master Plan, design,
and engineering services for the first and second phase of recreation improvements
identified in the master plan; NOW, THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
The Second Amendment to the Agreement for Professional Design/Consulting
Services between the City of Pueblo, a Colorado Municipal Corporation, and NorthStar
Engineering, a copy of which is attached, having been approved as to form by the City
Attorney, is hereby approved.
SECTION 2.
The Mayor is hereby authorized to execute and deliver said Agreement on behalf
of the City of Pueblo, a Colorado Municipal Corporation, and the City Clerk is authorized
to affix the Seal of the City thereto and attest same.
SECTION 3.
Funds in the amount of $24,800 for said professional services shall be paid from
Capital Project PL1703.
SECTION 4.
The officers and staff of the City are authorized to perform any and all acts
consistent with this Ordinance to implement the policies and procedures described herein.
SECTION 5.
This Ordinance shall become effective on the date of final action by the Mayor and
City Council.
Action by City Council:
Introduced and initial adoption of Ordinance by City Council on June 14, 2021 .
Final adoption of Ordinance by City Council on June 28, 2021 .
President of City Council
Action by the Mayor:
☒ Approved on June 30, 2021 .
□ Disapproved on based on the following objections:
_
Mayor
Action by City Council After Disapproval by the Mayor:
□ Council did not act to override the Mayor's veto.
□ Ordinance re-adopted on a vote of , on
□ Council action on _______ failed to override the Mayor’s veto.
President of City Council
ATTEST
City Clerk
City Clerk’s Office Item # R-4
BACKGROUND PAPER FOR PROPOSED
ORDINANCE
COUNCIL MEETING DATE: June 14, 2021
TO: President Lawrence W. Atencio and Members of City Council
CC: Nicholas A. Gradisar, Mayor
VIA: Marisa Stoller, City Clerk
FROM: Scott Hobson, Acting Director of Planning and Community Development
SUBJECT: AN ORDINANCE APPROVING THE SECOND AMENDMENT TO THE
PROFESSIONAL ENGINEERING SERVICES AGREEMENT BETWEEN
THE CITY OF PUEBLO, A COLORADO MUNICIPAL COPORATION, AND
NORTHSTAR ENGINEERING AND SURVEYING, INC. RELATING TO
THE DESIGN AND ENGINEERING OF THE ARKANSAS RIVER FLOOD
LEVEE MASTER PLANNING AND DESIGN AND AUTHORIZING THE
MAYOR TO EXECUTE SAME
SUMMARY:
This Ordinance approves and authorizes the Mayor to sign the Second Amendment for
professional design and engineering services related to the Arkansas River Flood Levee
Master Planning and Design, PL1703.
PREVIOUS COUNCIL ACTION:
On September 11, 2017, City Council approved an Agreement for professional
engineering services with NorthStar Engineering and Surveying, Inc. to complete a
recreation Master Plan for the Arkansas River Levee Corridor and design and engineering
for the first phase recreation improvements, Resolution 13769.
On March 23, 2020, City Council approved the First Amendment to the Professional
Engineering Services Agreement between the City and NorthStar Engineering and
Surveying, Inc. to complete design and engineering services for portions of the second
phase recreation improvements identified in the Arkansas River Levee Park Master Plan,
which include the Main Street pedestrian bridge, Westside Neighborhood Connections,
and site amenities.
BACKGROUND:
NorthStar Engineering and Surveying completed the Arkansas River Levee Park Master
Plan in December 2018 and design and engineering for the primary recreation
improvements identified in the master plan. The engineered improvements included the
th
Levee Trail, 4 Street pedestrian bridge, trail connection to the Grove Neighborhood,
Arkansas River access from the levee, and the safety ledge along the toe of the levee
within the Arkansas River Whitewater Park, which are being constructed with Great
Outdoors Colorado (GOCO), Connection Initiative, Department of Local Affairs
Energy/Mineral Impact (DOLA EIAF), and Colorado Department of Transportation,
Transportation Alternatives (CDOT TAP) Funding.
The First Amendment to the Professional Services Agreement provided design and
engineering services for the Main Street pedestrian bridge, Westside Neighborhood
Connections, and site amenities. These amenities are being constructed with DOLA EIAF
and GOCO funds.
The Second Amendment to the Professional Services Agreement will provide
construction administration, staking, and testing services for the shade structures that
were not included in the original project scope. Services that will be provided by NorthStar
th
Engineering include modifications to the concrete trail between the 4 Street and the
Union Avenue Bridges resulting from the project modification.
FINANCIAL IMPLICATIONS:
Funds in the amount of $24,800 shall be available from Project, PL1703 to pay for the
additional engineering services.
BOARD/COMMISSION RECOMMENDATION:
Not applicable.
STAKEHOLDER PROCESS:
Not applicable.
ALTERNATIVES:
The Arkansas River Levee Trail Main Street pedestrian bridge, Westside Neighborhood
Connections, and trail amenities will not be designed and constructed if this Ordinance is
not approved.
RECOMMENDATIONS:
Approval of the Ordinance.
Attachments:
Proposed Ordinance
Amendment No. 2 to the Agreement for Professional Design/Consulting Services
AMENDMENT NO. 2 TO THE
AGREEMENT FOR PROFESSIONAL DESIGN/CONSULTING SERVICES
This Amendment No. 2 to the Professional Design/Consulting Services Agreement
("Amendment") is executed to be effective as of June 28, 2021 by and between the City of Pueblo,
Colorado,a Colorado Municipal Corporation("Owner")and NorthStar Engineering and Surveying, Inc.,a
Colorado Corporation("Contractor"). Owner and Contractor are sometimes referred to herein as a"Party"
and collectively, as the"Parties." WITNESSETH THAT:
WHEREAS, Owner and Contractor entered into that certain Professional Design/Consulting
Services Agreement dated September 11,2017(the"Agreement"); and
WHEREAS, Owner and Contractor desire to modify the Agreement pursuant to the provisions set
forth herein.
NOW, THEREFORE, in consideration of the foregoing premises, the mutual promises set forth
herein and other good and valuable consideration, the receipt and adequacy of which is hereby
acknowledged, Owner and Contractor hereby agree to the following:
AGREEMENT
1. Scope of Services and Cost of Services. Contractor shall render services to prepare
construction documentation and engineering for additional services related to Phase 2 of the Arkansas River
Flood Levee Master Plan as specified in the Scope of Services for a total cost of$24,800 as indicated in the
Fee Schedule. Scope of Services and Fee Schedule are attached hereto and incorporated herein by this
reference.
2. Successors and Assigns. This Amendment shall be binding upon and inure to the benefit
of the Parties hereto and their respective successors and assigns.
3. Ratification. The Agreement dated September 11, 2017 is hereby ratified and except as
expressly stated herein,the Agreement shall remain in full force and effect. If there is any conflict between
the terms of the Agreement, and the terms of this Amendment,the terms of this Amendment shall control.
4. Counterparts. This Amendment may be executed in one or more counterparts, each of
which shall be deemed an original and all of which shall constitute one and the same document with the
same effect as if all Parties had signed the same original. The Parties further agree that transmission of this
Amendment by any electronic format,telecopy or via email in a PDF format, shall be deemed transmission
of the original Amendment for all purposes. Electronic signatures shall be deemed valid and binding to the
same extent as the original
(Signature Page Follows)
Bid 17-022 Amendment No.2 Page 1 of 3
IN WITNESS WHEREOF, the Parties to this Amendment No. 2 have set forth their hand, to be effective
as of the effective date.
CITY OF PUEBLO, NorthStar Engineering and Surveying, Inc.
A MUNICIPAL CORPORATION
By G,�� �C�� 1 By
Nicholas A. Gradisar �im Kock
Mayor President
Attest
C rk
[ SEAL ]
BALANCE OF APPROPRIATION EXISTS FOR
THIS CONTRACT AND FUNDS ARE AVAILABLE.
c,-.7/1a,e4,04,..kia,i, 6y/ .)4(/'
ir ctor of Finance
APPROVED AS TO FORM:
c,7 v,et_
City Attorney
Attachment: Letter from NorthStar Engineering and Surveying dated April 5, 2021
Including Scope of Services and Fee Schedule
Bid 17-022 Amendment No.2 Page 2 of 3
N O RT H �•�..��` T R
I IV(alNif Y-r Y'21NC: ANC) :UYt�if`YINC:,
Sernn9 Pueblo 8 So Golorardo Since 1939
IIV C .
111 E. 5th Street (719)544-6823
Pueblo, CO 81003 (719) 544-6825 Fax
Km Kock, P.E. Michael L Guppy, P.E.,E,,,, ,.
JN 12 008 04
Date April 5, 2021
City of Pueblo,
Depart of Planning and Community Development
111 E. D Street
Pueblo, CO 81003
Attn: Beritt Odom and Steven Meier
Via: Email bodom@pueblo.us, smeier@pueblo.us
Re: Additional Services for Arkansas River Flood Levee Master Planning and Design Project
- Phase 2 in the City of Pueblo, CO
NorthStar Engineering and Surveying, Inc. has completed all design services related to its
scope for the above referenced project($50,000.00 contract). As you are aware construction
administration, staking, testing, etc. services for the improvements associated with that scope
are being completed by us and CTL Thompson, Inc. under contract with the Pueblo
Conservancy District. The City of Pueblo is requesting that NorthStar(and CTL) complete
additional services on the project for an expanded scope of recreational improvements. That
work includes services related to new shade structures, trail modifications, and trail extensions.
Not only do our services include reviews, layout, and coordination of new shade structures
complete with trail redesigns and extensions, our work also includes: project improvement
estimating and coordination with the City grant funds; furnishing pricing information to the
project contractor and coordination of bid pricing with the contractor and the City; shop drawing
reviews; construction staking of the new structures; inspections and typical construction
administration services; and concrete and soils testing (CTL Thompson).
Project Fee including projected manhour allocation and reimbursable expenses:
a. Principal(PE/PLS): 40 hours @ $160.00 = $6,400.00
b. Project Engineer: 100 hours @$110.00 = $11,000.00
c. CAD Technician: 24 hours @ $70.00 = $1,680.00
d. Field Crew with GPS: 16 hours @ $150.00 = $2.400.00
e. Concrete and soils testing (CTL Thompson): $3,000.00
f. Bluelines, xerox, mileage and miscellaneous expenses: $320.00
TOTAL FEE: . $24,800.00
Bid 17-022 Amendment No.2 Page 3 of 3