RESOLUTION NO. 14500
A RESOLUTION RATIFYING AN EMERGENCY
CONSTRUCTION CONTRACT IN THE AMOUNT OF
$106,852.78 WITH PARKER EXCAVATING, INC. FOR
EMERGENCY SANITARY SEWER POINT REPAIR IN THE
ALLEY BEHIND 1427 EAST EVANS AVENUE, PROJECT
NO. 18-098 (WWAN03) AND APPROVING THE
PURCHASING AGENT’S EXECUTION OF SAME
WHEREAS, an emergency sanitary sewer repair was authorized by the Pueblo
City Mayor in accordance with Section 1-10-5 of the Pueblo Municipal Code; and
WHEREAS, the point repair work was awarded to Parker Excavating, Inc., under
the 2019-2020 multi-year point repair contract; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
City Council ratifies and approves the contract for repair of the sanitary sewer at
1427 East Evans Ave. with Parker Excavating Inc., Project No. 18-098 (WWAN03)
awarded to said bidder in the amount of $106,852.78.
SECTION 2.
Funds for Project 18-098 (WWAN03) shall be from the Sewer User Fund.
SECTION 3.
The Purchasing Agent is authorized to execute said contract on behalf of Pueblo,
a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and
attest the same.
SECTION 4.
The officers and staff of the City are directed and authorized to perform any and
all acts consistent with the intent of this Resolution and the contract to effectuate the
transactions described therein. Furthermore, all actions previously taken by officers and
staff of the City consistent with the contract including any payments authorized under
the contract are hereby ratified.
SECTION 5.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED November 9, 2020
BY: Ed Brown
MEMBER OF CITY COUNCIL
APPROVED:
PRESIDENT OF CITY COUNCIL
ATTESTED BY:
CITY CLERK
City Clerk’s Office Item # M-1
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: November 9, 2020
TO: President Dennis E. Flores and Members of City Council
CC: Nicholas A. Gradisar, Mayor
VIA: Brenda Armijo, City Clerk
FROM: Nancy Keller, Director of Wastewater
SUBJECT: A RESOLUTION RATIFYING AN EMERGENCY CONSTRUCTION CONTRACT
IN THE AMOUNT OF $106,852.78 WITH PARKER EXCAVATING, INC. FOR
EMERGENCY SANITARY SEWER POINT REPAIR IN THE ALLEY BEHIND
1427 EAST EVANS AVENUE, PROJECT NO. 18-098 (WWAN03) AND
APPROVING THE PURCHASING AGENT’S EXECUTION OF SAME
SUMMARY:
This Resolution ratifies and approves award of a construction contract to Parker Excavating,
Inc. for emergency sanitary sewer point repair at 1427 East Evans Ave.
PREVIOUS COUNCIL ACTION:
None
BACKGROUND:
On May 29, 2020, the Wastewater Department was notified that a customer at 1427 East Evans
Avenue was having sewer backup and slow drain issues. The Collection Division tried to clean
the line but encountered several blockages cleaning from both the upstream and downstream
manholes. The collections crew tried to perform an emergency TVI but was only able to go 10
feet from the upstream manhole and only 40 feet. from the downstream manhole.
The repair work was performed under the Sanitary Sewer Point Repair multi-year contract under
which three contractors were qualified via competitive bid An estimate was prepared and K.R.
Swerdfeger was the low bidder but declined the work due to being short staffed. Parker
Excavating was the next low bidder and accepted the work.
The cost breakdown for the project is as follows:
Sanitary Sewer Replacement-Related
Total: $ 67,002.38 63%
Surface Improvement Related
Total: $ 39,850.40 37%
Grand Total: $106,852.78 100%
FINANCIAL IMPLICATIONS:
Funding for this Project came from the sanitary sewer rehabilitation budget funded by the Sewer
User Fund. Funding was available and had previously been budgeted, appropriated and
allocated to Project No. 18-098 (WWAN03).
BOARD/COMMISSION RECOMMENDATION:
Not applicable
STAKEHOLDER PROCESS:
None
ALTERNATIVES:
Not approve this Resolution, but such action would require a finding that there was not an
emergency condition.
RECOMMENDATION:
Approval of the Resolution.
Attachments: Bid Summary Sheet
Change Order
Site Location Map
CONTRACT CHANGE ORDER
CITY OF PUEBLO DEPARTMENT OF PUBLIC WORKS
Project Number: 18-098 Change Order No. : ONE 8/24/2020 Page 1 of 1
Project Name : FY2019&2020 Sanitary Sewer Point Repair
1427 EVANS AVE.
Contractor: Parker Excavating, Inc.
You are hereby requested to comply with the following changes from the plans&specifications:
Bid Item Description of Changes Decrease Increase
No. Contract By Contract By
2 ASPHALT PATCH-4"HMA ON 4"CLASS 6 ABC FOR 8"AND 1 $4,000.00
3 REMOVE&REPLACE 7"REINFORCED CONCRETE ($2,584.40)
4 REMOVE&REPLACE STANDARD CURB&GUTTER ($370.00)
5 INSTALL EXTRA LEAN CONCRETE(FLOW FILL) $513.00
6 REMOVE&REPLACE 48"DIA.MANHOLE $4,117.00
7 REINSTATE SERVICES $1,175.00
8 MOBILIZATION $750.00
9 TRAFFIC CONTROL $3,901.11
10 CLEAN-UP FROM WATER WORKS-LABOR AND BROOM $1,387.00
11 MILL $918.40
12 RE-DIG AND REPAIR DUE TO NO TRAFFIC CONTROL $2,724.00
13 EXTTRA ROCK $1,547.67
TOTAL (Decrease)/Increase ($2,954.40) $21,033.18
Net Adjustment This Change Order $ 18,078.78
Amount of Previous Change Order(s) $ 0.00
Original Contract Amount $ 88,774.00
Total Adjusted Contract Amount To Date $ 106,852.78
Reason For Change: Actual Field Quantities.
Extra work needed to complete project
The time provided for completion of the contract is changed by 0 calendar days.
This document shall become an amendment to the contract and all provisions of the contract apply hereto.
Prepared by: Date:
Associate Engineer I
Reviewed by: Date:
Wastewater Engineering Manager
Accepted by: Date:
Contractor's Representative
If this Change Order causes an increase from the original contract price,signed approval by the Director
constitutes representation that lawful appropriations are sufficient to cover such increase.
Approved by: Date:
Director of Wastewater
FORM CO100.1299
-W -- E x�� %
E
i
Si '64..r•''_.:1
" � ....
N� „
Y ° "� �
, iT Ner /N ` ''- .
f t ' Wil. ' a '• ''-'.." --- "i
- -• ' P'; , ,., ,--1-, 7i., '-).,- .
W NORTHERN AVE
a;` i . y " , 'l_ C.Z.
ce
i .0 Or j� Z
4,.4
4, �4 W
' r . it `,� -.. .moi W
1. tt
'� VI ,at' .l• , * „„, J
H ..
40R.. 1 4 V
W tri,
t t
6 1 » MCCULLEY AVE .-- - '4,----e,- �=.
.i" ();,r_.- .
#, "' a:, ,t r F , aim 'O •
sj / � 1 t 11.4i-1,,,j•-:. t -
� ,. it 4e i'll c rt
14 • ,.... '1/4 ‘ ;r ,
4 10
:t:
..:-r,, ,...4.7„, 1 i ;7 ,•�1!7J '144.: S14
'i '.t _ K
c
• i - 4, DIVISIONm
.,,,,,,,„:,,,,t7,4,,,,,,,,t 6
1r 5' 1 4,'-' '.-A ' `, . r
z
� '� � f • �� A
f t,r ".
6
DIVISION "AVE . -. .,,_ Q A.' lit edit t. t. m
� '
W Com, � t O
i f
Z „ '
•
• k . �,�
..,.. . if'.",..‘..i li :' ,
'-a r i ‘ l$ . W m
4 . W i ire.-_ IF * 4 -C
-. tE _1 , Q r - �4' '-. G
o m
.� 0 1
■• . Z i 1 z 0
e� - Ir)
a W m
s °, 484372 8 W Q
�"' tSTATEAVE
�. .— a►.i - .�„ W _ t
BAYAV
V, �, ��. �) . .,
-+" Y tClpi�"i f f * to
- .fit e. 4 _...
•.,. '- - ' i. ._
�Disclaimer:l This map/information has been produced by the City of Pueblo,Wastewater Department,and is for
I_ Data provided herein is derived from sources with varying levels of accuracy.The City of Pueblo
' ,. t t,. -' t responsibility for the accuracy or completeness of the information contained herein.