HomeMy WebLinkAbout14020
RESOLUTION NO. 14020
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT
IN THE AMOUNT OF $706,251 TO LAYNE INLINER LLC, AND
SETTING FORTH $141,250 FOR CONTINGENCIES, FOR
PROJECT 18-065 (WWAN02) 2018 NORTHERN LARGE MAIN
LINING PROJECT AND AUTHORIZING THE PURCHASING
AGENT TO EXECUTE THE SAME
WHEREAS, competitive bids for the Project No. 18-065 (WWAN02) 2018 Northern Large
Main Lining Project have been received and examined; and
WHEREAS, the proposal of Layne Inliner LLC, of Kiowa, Colorado was the lowest of those
bids determined to be responsive; NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
This contract is for lining 2,385 linear feet of pipe and 137 vertical feet of epoxy for
manholes. Contract Agreement for 2018 Northern Large Main Lining Project with Layne Inliner
LLC, Project No. 18-065 (WWAN02) is hereby awarded to said bidder in the amount of $706,251.
SECTION 2.
Funds for Project 18-065 (WWAN02) shall be from the Sewer User Funds.
SECTION 3.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
A Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 4.
In addition to the amount of the bid set forth, as aforementioned, an additional amount as
stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work……...$141,250
SECTION 5.
The officers and staff of the City are directed and authorized to perform any and all acts
consistent with the intent of this Resolution and the contract to effectuate the transactions
described therein.
SECTION 6.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED: August 13, 2018
BY: Ed Brown
MEMBER OF CITY COUNCIL
APPROVED:
PRESIDENT OF CITY COUNCIL
ATTESTED BY:
ACTING CITY CLERK
City Clerk’s Office Item # M-1
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: August 13, 2018
TO:
President Christopher A. Nicoll and Members of City Council
CC:
Sam Azad, City Manager
VIA:
Brenda Armijo, Acting City Clerk
FROM:
Nancy Keller, Wastewater Director
SUBJECT:
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT
OF $706,251 TO LAYNE INLINER LLC, AND SETTING FORTH $141,250 FOR
CONTINGENCIES, FOR PROJECT 18-065 (WWAN02) 2018 NORTHERN
LARGE MAIN LINING PROJECT AND AUTHORIZING THE PURCHASING
AGENT TO EXECUTE THE SAME
SUMMARY:
This Resolution awards a construction contract to Layne Inliner LLC, for 2018 Northern Large
Main Lining Project. The project will place Ultra Violet Cured-In-Place pipe in severely deteriorated
large diameter reinforced concrete pipe.
PREVIOUS COUNCIL ACTION
:
None
BACKGROUND
:
The Wastewater Department evaluated all the large diameter reinforced concrete pipes and found
that they were all over 35 years old and were severely deteriorated. This project will rehabilitate
the large diameter reinforced concrete pipes for the Northern Avenue Outfall, located on Northern
Avenue from Prairie Avenue to approximately Vassar Avenue. The project consists of 2,385 lineal
feet of Cured-in-Place pipe and all connected manholes will be epoxy coated.
FINANCIAL IMPLICATIONS
:
The cost of the construction project was bid at $706,251 with contingencies of $141,250. Funds
are available from the Sewer User Funds and have been budgeted and appropriated to Project
No. 18-065 (WWAN02).
BOARD/COMMISSION RECOMMENDATION
:
Not applicable
STAKEHOLDER PROCESS
:
None
ALTERNATIVES
:
Alternative No. 1 – No Action
Under this alternative, the City would do no improvements to the existing sanitary main. The
system would continue to deteriorate until failure, at which time an emergency repair would be
.
performed
Alternative No. 2 – Complete Remove and Replace
Under this alternative, the City would completely remove and replace all main segments and
manholes. Roads would be torn up to remove the existing and place new pipe. Trenches would
need to be backfilled and roads rebuilt.
Alternative No. 3 – Sliplining the Existing Pipe
Under this alternative, the City would need to dig access pits at each manhole and a smaller
pipe would be pushed through the existing pipe. The space between the new and old pipe would
need to be filled with a slurry mix. This method would reduce the capacity of flow in the mains.
All the alternatives would be significantly more expensive and would impact the flow of traffic more
than the preferred alternative.
RECOMMENDATION
:
Approval of the Resolution.
Attachments
:
Bid Summary Sheet
Site Location Map