HomeMy WebLinkAbout13927
RESOLUTION NO. 13927
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN
THE AMOUNT OF $49,460.00 TO CEDAR RIDGE LANDSCAPE,
INC., AND SETTING FORTH $9,000.00 FOR CONTINGENCIES
AND ADDITIONAL WORK FOR PROJECT NO. 18-034 – ST.
ANNE’S PARK PLAYGROUND (CDBG) PROJECT, AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE
SAME
WHEREAS, proposals for PROJECT NO. 18-034, St. Anne’s Park Playground (CDBG)
Project, have been received and examined, and;
WHEREAS, the proposal of Cedar Ridge Landscape, Inc., of Pueblo, Colorado was the
lowest of those bids determined to be responsible; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract for PROJECT NO. 18-034 (CD1712), St. Anne’s Park Playground (CDBG)
Project, is hereby awarded to said bidder in the amount of $49,460.00.
SECTION 2.
In addition to the amount of the bid set forth, as aforementioned, an additional
amount of $9,000.00 is hereby authorized for contingencies and additional work.
SECTION 3.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 4.
The officers and staff of the City are directed and authorized to perform any and all acts
consistent with the intent of this Resolution to effectuate the policies and procedures described
herein.
SECTION 5.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED March 26, 2018
BY: Ed Brown
MEMBER OF CITY COUNCIL
APPROVED:
PRESIDENT OF CITY COUNCIL
ATTESTED BY:
ACTING CITY CLERK
City Clerk’s Office Item # M-3
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: March 26, 2018
TO: President Christopher A. Nicoll and Members of City Council
CC: Sam Azad, City Manager
VIA: Brenda Armijo, Acting City Clerk
FROM: Jeff Bailey P.E., Acting Director of Public Works
SUBJECT: A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT
OF $49,460.00 TO CEDAR RIDGE LANDSCAPE, INC., AND SETTING FORTH
$9,000.00 FOR CONTINGENCIES AND ADDITIONAL WORK FOR PROJECT
NO. 18-034 – ST. ANNE’S PARK PLAYGROUND (CDBG) PROJECT, AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
SUMMARY:
This resolution awards a Construction Contract to Cedar Ridge Landscape, Inc., for the St. Anne’s
Park Playground Project.
PREVIOUS COUNCIL ACTION:
None.
BACKGROUND:
In general, this project will consist of the excavation and grading of new playground area,
installation of gravel sump, construction of 6”x18” curb head, installation of new pre-purchased
playground equipment, installation of new pre-purchased safety surfacing, construction of new 4”
concrete and other incidental items related to the construction as detailed in the plans and
specifications for this project.
FINANCIAL IMPLICATIONS:
Funds for the Project will be paid out of CD -1712 St. Anne’s Playground (CDBG).
BOARD/COMMISSION RECOMMENDATION:
Not Applicable
STAKEHOLDER PROCESS:
None
ALTERNATIVES:
Denying the Resolution will result in cancellation of the project.
RECOMMENDATION
:
Approval of the Resolution.
Attachments:
Bid Summary