HomeMy WebLinkAbout13856
RESOLUTION NO. 13856
A RESOLUTION AWARDING A CONSTRUCTION
CONTRACT IN THE AMOUNT OF $489,403 TO K.R.
SWERDFEGER CONSTRUCTION, INC. AND SETTING
FORTH $97,880.60 FOR CONTINGENCIES, FOR
PROJECT NO. 17-014 (WWAN01) FY2017 SMALL MAIN
REHAB AND AUTHORIZING THE PURCHASING AGENT
TO EXECUTE THE SAME
WHEREAS, competitive bids for the Project No. 17-014 (WWAN01) FY2017
Small Main Rehab have been received and examined; and
WHEREAS, the proposal of K.R. Swerdfeger Construction, Inc. of Pueblo,
Colorado was the lowest of those bids determined to be responsive; NOW
THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
This contract is for removing and replacing approximately 2129 lineal feet of
deteriorated small sanitary sewer mains. Contract Agreement forFY2017 Small Main
Rehab with K.R. Swerdfeger Construction, Inc., Project No. 17-014 (WWAN01) is
hereby awarded to said bidder in the amount of $489,403.
SECTION 2.
Funds for Project 17-014 (WWAN01) shall be from the Sewer User Funds.
SECTION 3.
The Purchasing Agent is hereby authorized to execute said contract on behalf of
Pueblo, A Municipal Corporation, and the City Clerk shall affix the seal of the City
thereto and attest the same.
SECTION 4.
In addition to the amount of the bid set forth, as aforementioned, an additional
amount as stipulated in this section is hereby established for contingencies and
additional work.
Contingencies and Additional Work………$97,880.60
SECTION 5.
The officers and staff of the City are directed and authorized to perform any and
all acts consistent with the intent of this Resolution and the contract to effectuate the
transactions described therein.
SECTION 6.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED December 26, 2017
BY: Ed Brown
City Clerk’s Office Item # M-6
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: December 26, 2017
TO:
President Stephen G. Nawrocki and Members of City Council
CC:
Sam Azad, City Manager
VIA:
Brenda Armijo, Acting City Clerk
From:
Nancy Keller, Wastewater Director
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
SUBJECT:
AMOUNT OF $489,403 TO K.R. SWERDFEGER CONSTRUCTION, INC.
AND SETTING FORTH $97,880.60 FOR CONTINGENCIES, FOR
PROJECT NO. 17-014 (WWAN01) FY2017 SMALL MAIN REHAB
PROJECT AND AUTHORIZING THE PURCHASING AGENT TO
EXECUTE THE SAME
SUMMARY:
Attached is a Resolution awarding a construction contract to K.R. Swerdfeger
Construction, Inc. for Project No. 17-014 (WWAN01), FY2017 Small Main Rehab. The
project will remove and replace the deteriorated Small Sewer Mains and Manholes for
the sites listed below.
PREVIOUS COUNCIL ACTION
:
None
BACKGROUND
:
The Wastewater Department maintains a priority list of deteriorating sanitary sewer
mains. All of the sites on the project were taken from this list due to their deteriorated
structural condition. To protect the public interest these mains require rehabilitation.
This project is not related to sealing sanitary sewers for selenium reduction.
The cost breakdown for the project is as follows:
Site Description Sewer Surface Council
Related Related District
1 Winnipeg St. and Mirror Ave. $79,070.00 $61,062.00 4
2 Acero Ave. and Mirror Ave. $121,310.00 $92,178.00 4
th
3 Queens Ave. and E. 15 St. $43,669.00 $4,732.00 2
4 Hillside Dr. and Hillside Ct. $48,858.00 $25,344.00 1
th
5 West St. and W. 8 St. $13,180.00 $0.00 2
Totals $306,087.00 $183,316.00
62%38%
Project %
The total cost of the project is estimated at $587,283.60, including contingencies.
FINANCIAL IMPLICATIONS
:
The cost of the construction project was bid at $489,403 with contingencies of
$97,880.60. Funds are available from the Sewer User Funds and have been budgeted
and appropriated to Project No. 17-014 (WWAN01).
BOARD/COMMISSION RECOMMENDATION
:
Not applicable
STAKEHOLDER PROCESS
:
None
ALTERNATIVES
:
Alternative No. 1 - No Action
If no rehabilitation is performed on the collection system, the condition of the sanitary
mains would continue to deteriorate until an emergency repair is required. The
Wastewater Department would also risk violating its discharge permit if a sanitary sewer
overflow were to happen.
RECOMMENDATION
:
Approval of the Resolution.
Attachments
: Bid Summary Sheet
Site Location Map
SITE#4 HILLSIDE DR.
SITE#3 QUEENS AVE.
0
0 SITE#5 WEST ST.
SITE#1 VVINNEPEG ST.
dw SITE 42 ACERQ AVE.