HomeMy WebLinkAbout13116RESOLUTION NO. 13116
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT
IN THE AMOUNT OF $62,562.97 TO PARKER EXCAVATING
INC., FOR EMERGENCY SANITARY SEWER POINT REPAIR IN
THE INTERSECTION OF SOUTH SANTA FE AVENUE AND
ALAN HAMEL AVENUE AND AUTHORIZING THE
PURCHASING AGENT TO EXECUTE THE SAME
WHEREAS, an emergency sanitary sewer repair was authorized by the Pueblo City
Manager in accordance with Section 1-10-5 of the Pueblo Municipal Code ; and
WHEREAS, the point repair work was awarded to Parker Excavating Inc., under the
2013-2014 multi-year point repair contract ; NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
This contract is for repair of the sanitary sewer main in the intersection of South Santa
Fe Avenue and Alan Hamel Avenue. Contract Agreement for Sanitary Sewer Repair with Parker
Excavating Inc., Project No. 13-012 (WWAN03) is hereby awarded to said bidder in the amount
of $62,562.97.
SECTION 2.
Funds for Project 13-021 (WWAN03) shall be from the Sewer User Fund.
SECTION 3.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 4.
The officers and staff of the City are directed and authorized to perform any and all acts
consistent with the intent of this Resolution and the contract to effectuate the transactions
described therein. Furthermore, all actions previously taken by officers and staff of the City
consistent with the contract including any payments authorized under the contract are hereby
ratified.
SECTION 5.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED: November 24, 2014
BY: Eva Montoya
City Clerk’s Office Item # M-15
Background Paper for Proposed
Resolution
COUNCIL MEETING DATE: November 24, 2014
TO: President Stephen G. Nawrocki and Members of City Council
CC: Sam Azad, City Manager
VIA: Gina Dutcher, City Clerk
From: Gene Michael, Wastewater Director
SUBJECT:
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $62,562.97 TO PARKER EXCAVATING INC., FOR
EMERGENCY SANITARY SEWER POINT REPAIR IN THE
INTERSECTION OF SOUTH SANTA FE AVENUE AND ALAN HAMEL
AVENUE AND AUTHORIZING THE PURCHASING AGENT TO
EXECUTE THE SAME
SUMMARY:
Attached is a resolution awarding a construction contract to Parker Excavating Inc., for
emergency sanitary sewer point repair at the intersection of South Santa Fe Avenue
and Alan Hamel Avenue.
PREVIOUS COUNCIL ACTION
:
None
BACKGROUND
:
On June 10, 2014, the Wastewater Department discovered that the 60-inch diameter
manhole in the intersection of South Santa Fe Avenue and Alan Hamel Avenue was
significantly deteriorated and in need of immediate attention. A televised inspection of
the manhole showed the manhole to be in imminent danger of collapse due to
significant amounts of hydrogen sulfide (HS) which causes deterioration of concrete
2
and metal. Therefore, it was determined that the manhole needed to be replaced. In
addition, after further field inspection and research, it was determine that the 15-inch
main feeding into the manhole needed to be replaced. Parker Excavating was asked to
install a new 48-inch diameter manhole, a new 60-inch diameter manhole and
approximately 45 lineal feet of 15-inch PVC pipe to guarantee collapse did not occur
and to ensure public health and safety.
The quote for the unit prices for the work by Parker Excavating Inc. and the change
order for the project are attached. This work was performed under the Sanitary Sewer
Point Repair multi-year contract under which nine (9) contractors were qualified via
competitive bid. During the project the costs were modified by actual field quantities as
noted on the attached change order.
The cost breakdown for the project is as follows:
Sanitary Sewer Replacement-related
Remove & Replace 15" PVC < 12' $3,105.00
Remove & Replace 60-inch Dia.
Manhole with Xypex $4,784.37
Traffic Control $25,000.00
Bypass Pumping $6,000.00
T&M Looking for Manhole $1,760.00
T&M Breaking into 72-inch Line $2,240.00
Mobilization $800.00
70%
Subtotal: $43,689.37
Surface Improvement-related
Asphalt Patch – 6-inch Full Depth
Asphalt, 21-100 SF $4,176.00
Mobilization for Overlay $1,700.00
Milling $3,980.00
Asphalt Overlay $4,176.00
Flowfill $4,841.60
30%
Subtotal: $18,873.60
TOTAL: $62,562.97
FINANCIAL IMPLICATIONS
:
Funding for this project will come from the sanitary sewer rehabilitation budget funded
by the Sewer User Fund. Funding was available and had been budgeted, appropriated
and allocated to Project No. 13-012 (WWAN03).
BOARD/COMMISSION RECOMMENDATION
:
Not applicable
STAKEHOLDER PROCESS
:
None
ALTERNATIVES
:
Alternative No. 1 – No Action
Under this alternative, the City would make no improvements to the existing sanitary
system and the 60-inch manhole would continue to deteriorate. This would eventually
lead to raw sewage exiting the main and increasing the risk for collapse in the middle of
Santa Fe Avenue and endangering public health and safety.
Alternative No. 2 – Place the Manhole and 15-inch Main on the Rehabilitation List
Under this alternative, the City would make no immediate improvements to the existing
sanitary system. The manhole and 15-inch main would be put on a rehabilitation list and
prioritized by the level of importance for future rehabilitation projects. Again, there would
be a risk that further decay of the 60-inch manhole would occur and eventually lead to
raw sewage exiting the main and increasing the risk for collapse in the middle of Santa Fe
Avenue and endangering public health and safety.
RECOMMENDATION
:
Approval of the Resolution.
Attachments
: Bid Summary Sheet
Change Order
Site Location Map
CONTRACT CHANGE ORDER
CITY OF PUEBLO DEPARTMENT OF WASTEWATER
Project Number: 13-012 Change Order No. : ONE 6/26/2014 Page 1 of 1
Project Name: MANHOLE AND 15"LINE AT 241 S. SANTA FE AVE.
Contractor: PARKER EXCAVATING INC.
You are hereby requested to comply with the following changes from the plans&specifications:
Bid Item - Description of Changes Decrease Increase
No. Contract By Contract By
r
1 ASPHALT PATCH-6"FULL DEPTH ASPHALT $986.00
2 R&R 48" DIAMETER MANHOLE ($2,950.00)
3 FLOWFILL-41 YDS FILL 4' ($3,280.00)
4 T&M LOOKING FOR MANHOLE $1,760.00
5 R&R 60"MANHOLE WITH XYPEX $4,784.37
6 FLOWFILL $4,841.60
7 MOBILIZATION FOR OVERLAY $1,700.00
8 T&M BREAKING INTO 72"LINE $2,240.00
9 MILLING $3,980.00
10 ASPHALT OVERLAY $4,176.00
TOTAL (Decrease)/Increase ($6,230.00)1 $24,467.971
Net Adjustment This Change Order $ 18,237.97
Amount of Previous Change Order(s) $ 0.00
Original Contract Amount $ 44,325.00
Total Adjusted Contract Amount To Date $ 62,562.97
Reason For Change: Actual Field Quantities and Conditions.
The time provided for completion of the contract is unchanged t by 0 calendar days.
This document shall become an amendment to the` contract and all provisions of the contract apply hereto.
Prepared by: rca..c.... (_. ,m, Date:Date: 8/i t /,2i !�/
�� soat=. •.'
Reviewed by: ast= Date:` tt/J4$$
w- gi r Supervisor
Accepted by: �/; Date: AV/)/V
C• racto s Representative
If this Change Order causes an increase from the original contract price, signed approval by the Director
constitutes representation that lawful appropriations are sufficien totcover such increase.
Approved by:
5-z.o.f,C �',. '�-et' . ---- Date: ` �
�Il //¢..
Dire or of Wastewater
FORM CO100.1299