HomeMy WebLinkAbout12879RESOLUTION NO. 12879
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT
IN THE AMOUNT OF $57,741.40 TO PARKER EXCAVATING
INC., FOR EMERGENCY SANITARY SEWER POINT REPAIR IN
THE ALLEY BETWEEN CEDAR STREET AND PINE STREET
FROM INDIANA AVENUE TO MINNEQUA AVENUE, AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE
SAME
WHEREAS, an emergency sanitary sewer repair was authorized by the Pueblo City
Manager in accordance with Section 1-10-5 of the Pueblo Municipal Code; and
WHEREAS, the point repair work was awarded to Parker Excavating Inc., under the
2013-2014 multi-year point repair contract; NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
This contract is for repair of the sanitary sewer main in the alley between Cedar Street
and Pine Street from Indiana Avenue to Minnequa Avenue. Contract Agreement for Sanitary
Sewer Repair with Parker Excavating Inc., Project No. 13-012 (WWAN03) is hereby awarded to
said bidder in the amount of $57,741.40.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
Funds for Project No. 13-012 (WWAN03) shall be from the Sewer User Fund.
SECTION 4.
The officers and staff of the City are directed and authorized to perform any and all acts
consistent with the intent of this Resolution and the contract to effectuate the transactions
described therein.
SECTION 5.
This Resolution shall become effective immediately upon passage and approval.
INTRODUCED: January 27, 2014
BY: Ami Nawrocki
Councilperson
Background Paper for Proposed
RESOLUTION
DATE: January 27, 2014 AGENDA ITEM # M-3
DEPARTMENT: WASTEWATER DEPARTMENT
GENE MICHAEL, DIRECTOR
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$57,741.40 TO PARKER EXCAVATING INC., FOR EMERGENCY SANITARY SEWER POINT
REPAIR IN THE ALLEY BETWEEN CEDAR STREET AND PINE STREET FROM INDIANA
AVENUE TO MINNEQUA AVENUE, AND AUTHORIZING THE PURCHASING AGENT TO
EXECUTE THE SAME
ISSUE
Should the City Council award a construction contract in the amount of $57,741.40 to Parker
Excavating Inc., for emergency sanitary sewer repair in the alley between Cedar Street and
Pine Street from Indiana Avenue to Minnequa Avenue?
RECOMMENDATION
Approve this Resolution.
BACKGROUND
On December 13, 2013 the Wastewater Department was made aware of a water main break in
the area of Cedar Street and Indiana Avenue. It is routine to have a sanitary sewer main
televised following a nearby water main leak to make sure that the sewer main is still intact and
functioning. Unfortunately in this instance, the sanitary sewer main was washed out and the
part of the main that was intact was full of water. As a result of the water main break the
sanitary sewer main was compromised and required immediate rehabilitation.
The quote for the unit prices for the work by Parker Excavating Inc. and the change order for the
project are attached. This work was performed under the Sanitary Sewer Point Repair multi-
year contract under which nine (9) contractors were qualified via competitive bid. During the
project the costs were modified by actual field quantities as noted on the attached change order.
The cost breakdown for the project is as follows:
Sanitary Sewer Replacement-related
Remove & Replace 8" PVC < 15' $21,838.00
Remove & Replace 48" Dia. Manhole $2,950.00
Reinstate Services $3,200.00
Galvanized Water Service $2,500.00
La Veta Point Repair $2,295.00
Traffic Control $2,100.00
Bypass Pumping $2,010.40
Mobilization $800.00
65%
Subtotal: $37,693.40
Surface Improvement-related
Asphalt Patch 4" on 6" Class 6 ABC $20,048.00
35%
Subtotal: $20,048.00
TOTAL: $57,741.40
FINANCIAL IMPACT
Funding for this project will come from the sanitary sewer rehabilitation budget funded by the
Sewer User Fund. Funding is available and has been appropriated and allocated to Project No.
13-012 (WWAN03).
CONTRACT AGREEMENT
• For
Emergency Sanitary Sewer Repair
THIS AGREEMENT made and entered into this 16th day of December, 2013, by and between the City of
Pueblo, a Municipal Corporation, hereinafter referred to in the Contract Documents as the "City ", and Parker
Excavating, Inc., referred to in the Contract Documents as "Contractor ".
WITNESSETH: In consideration of the sum to be paid by the City to the Contractor at the time and in
the manner hereinafter provided, the said Contractor has agreed, and does hereby agree, to furnish all
labor, tools, equipment and material and to pay for all such items, and to construct complete in every
detail, To -Wit:
Project No. 13 -012 (WWANO3)
FY2013 and 2014 Sanitary Sewer Point Repair
Sanitary Sewer Point Repair in the Alley between
Cedar & Pine, Indiana- Minnequa
At the prices bid in Article 1.B. Request for Quotation form, in accordance with the drawings and
specifications, and all Contract Documents for this project which are on file and available for inspection in
the office of the Director of Wastewater, all to the satisfaction of the Director of Public Works for the City of
Pueblo, Colorado
AND FOR SAID CONSIDERATION IT IS FURTHER AGREED BY AND BETWEEN THE PARTIES TO
THIS AGREEMENT AS FOLLOWS:
1. Construction and installation of the above enumerated work for the City shall be completed and
ready for use in accordance with the time of completion described in the Notice to Proceed for the
Sub - Project. This time shall be extended only for those periods set forth in the Contract Documents
and in accordance with the requirements of same.
2. The work and material for the Project covered by the Contract Documents shall be completely
installed and delivered to the City within the time above stated, clear and free from any and all liens,
claims and demands of any kind. Wherever in the Contract Documents the term "Project" is used, it
shall be taken to mean this Sub - project.
3. The full compensation to be paid to the Contractor by the City, pursuant to the terms of this Contract,
shall be payable as provided in the Contract Documents.
4. This Contract consists of the following component parts and documents, all of which taken together
constitute and are referred to as the Contract Documents, and the same are incorporated as part of
the Contract as if set out herein verbatim, whether the same have been attached hereto or not:
A. Request for Quotations
B. This Contract Agreement
C. General Conditions of the Contract — Article 3
D. Special Conditions
E. The Standard Construction Specifications and Standard
Details for City of Pueblo, Colorado, (most current edition in
effect on date of bid opening), are hereby included by
reference and all provisions thereof shall be applicable. By
submitting his bid, the Contractor acknowledges that he
possesses a copy of said document.
5. Title XII, Chapter 2, of the 1971 Code of Ordinances, City of Pueblo, adopted by Ordinance No.
3476, and amended by Ordinance No. 4476 and 5229, shall be considered a part of this contract.
6. Title I, Chapter 8, of the 1971 Code of Ordinances, City of Pueblo, adopted by Ordinance No. 4479,
shall be considered a part of the contract.
7. All of the covenants and agreements set forth in the Contract Documents shall inure to the benefit of
and be binding upon City and Contractor and their respective heirs, legal successors and assigns
and shall be governed by the laws of the State of Colorado.
8. Payment and Performance Bonds will not be required for this project if the bid amount is less than
$50,000.00 (per §38 -26 -106, C.R.S.). Progress payments will not be made, and a single payment
all work will be made upon completion of the entire Project and verification is made that it has been
inspected and approved by authorized Wastewater personnel.
IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed in four (4)
original counterparts as of the day and year first above written.
Parker Exc vatinq, Inc.
Contractor 4
1 J "l
� �
( d i i �b . Title V
,„:. ��.,., ,. y PUEBL- , . UNICIPAL CORPORATION
biligill n
o� By /ti t
Purchasing Agent
ATTEST:
■-i.,,....0.–
City Clerk
BALANCE OF APPROPRIATION EXISTS FOR
THIS CONTRACT FUNDS ARE AVAILABLE:
6r praL 11/10.4
—^
Director of Finance
APPROVED AS TO FORM:
0 4A....., a ,-
City Attorney
ARTICLE 1
B. REQUEST FOR QUOTATIONS
PROJECT NO.: 13 -012 (WWANO3)
PROJECT NAME: Point Repair — Alley btn Cedar & Pine Avenues, Indiana - Minnequa Avenues
All proposals are to be prepared on this form. All blank spaces must be correctly filled in where
indicated for each and every item for which a quantity is given, and the bidder must state the prices
(written in ink or typewritten) for which he proposes to do each item of the work contemplated or
furnish each item of the materials required.
The undersigned, having become familiar with the local conditions affecting the cost of the
work, and with the contract documents, including advertisement for bids, the form of proposal, the form
of contract, form of bond, special provisions of the contract, general provisions of the contract, etc.,
plans, drawings and specifications, issued and attached to the contract documents on file in the office
of the Purchasing Agent, hereby proposes to furnish all of the labor, materials, necessary tools and
equipment and all utility and transportation service necessary to perform and complete in a
workmanlike manner all of the work required in connection with the construction of an Emergency
Repair in the Alley btn Cedar & Pine Avenues, Indiana - Minnequa Avenues in accordance with the
plans and specifications as prepared by or for the City of Pueblo, Colorado, for the sums set forth in
the following bidding schedule:
BID ESTIMATED UNIT
ITEM DESCRIPTION QUANTITY PRICE AMOUNT
Alley btn Cedar & Pine Avenues, Indiana - Minnequa Avenues
1 Remove & Replace 8" PVC < 8' 330 LF $ 56.00 $ 18,480.00
2 Remove & Replace 4" Asphalt 330 LF $ 56.00 $ 18,480.00
3 Remove & Replace 48" Manhole 1 EA $ 2,950.00 $ 2,950.00
4 Reinstate Services 13 EA $ 200.00 $ 2,600.00
5 Mobilization 1 LS $ 800.00 $ 800.00
GRAND TOTAL BID $ 43.310.00
(Forty -three Thousand Three Hundred and Ten dollars and Zero cents)
The Grand Total Bid shall be the basis for establishing the amount of the performance bond for
this contract. The total bid is based on quantities shown on the proposal form and on the dimensions
shown on the plans, and is subject to additions or reductions according to the actual construction
quantities as determined by the Engineer upon completion of the construction.
The City reserves the right to adjust the required quantities and the contractor shall furnish said
quantities at the unit price quoted above. The time allowed for construction shall be adjusted in direct
proportion of the adjusted quantities to the estimated quantities.
The undersigned has carefully checked the above quantities against the plans and specifications
Page 1 of 2
C- ART1 -B; 1 -13 -2003
before preparing this proposal and accepts the said quantities as substantially correct, both as to
classification and amount, and as correctly listing the work to be done in accordance with the plans
and specifications.
The bidder must sign his proposal correctly and in ink; if the proposal is offered by an individual,
his name, office and post office address must be shown. If made by a firm or partnership, the name,
office and post office address of each member of the firm or partnership must be given; if offered by a
corporation, the person signing the proposal must give the name of the state under the laws of which
the corporation was chartered, and the name, title and business address of the President, Secretary
and the Treasurer. Anyone signing a proposal as agent must file legal evidence of his authority to do
so, and that the signature is binding upon the firm or corporation.
The undersigned, if awarded the contract, agrees to complete and file the complete contract and
performance bond in quadruplicate within ten (10) days of the date of Notice of Award, and further
agrees to complete the work within sixteen (21) calendar days of Notice to Proceed.
Liquidated damages will be assessed in accordance with Section 3.54 of ARTICLE 3 -
GENERAL PROVISIONS, for every calendar day thereafter until the work is complete and accepted by
the City of Pueblo.
NOTE: Bidders should not add any conditions or qualifying statements to this bid as
otherwise the bid may be declared irregular as being not responsive to the
advertisement for bids.
The contractor shall be subject to all applicable City, County, State and
Federal Taxes in the performance of this contract.
Firm Name : Parker Excavating
Business Address : 1428 Stockyard Road
Pue• o, CO 81001
By : XOF /1/7/4
Title : V,
Date : AV/ 7/3 Tele. No.: 719 - 545 -3010
Fax No.: 719 - 545 -0805
Contractor's Federal I.D. Number : 84- 0924766
Page 2 of 2
C- ART1 -B; 1 -13 -2003
CONTRACT CHANGE ORDER
CITY OF PUEBLO DEPARTMENT OF PUBLIC WORKS
Project Number : 13 -012 Change Order No.: ONE 1/6/2014 Page 1 of 1
Project Name : SANITARY SEWER POINT REPAIR IN ALLEY BTN CEDAR & PINE
INDIANA- MINNEQUA
Contractor : PARKER EXCAVATING, INC.
You are hereby requested to comply with the following changes from the plans & specifications:
Bid Item Description of Changes Decrease Increase
No. Contract By Contract By
1 R &R 8" VCP TO PVC <8' ($18,480.00)
2 ASPHALT PATCH 4" ON 6" CLASS 6 ABC $1,568.00
4 REINSTATE SERVICES $600.00
6 R &R 8" VCP TO PVC <12' $21,838.00
7 GALVANIZED WATER SERVICE $2,500.00
8 TRAFFIC CONTROL $2,100.00
9 BYPASS PUMPING $2,010.40
10 LA VETA POINT REPAIR $2,295.00
TOTAL (Decrease) / Increase I $18,480.00 $32,911.40
Net Adjustment This Change Order $ 14,431.40
Amount of Previous Change Order(s) $ 0.00
Original Contract Amount $ 43,310.00
Total Adjusted Contract Amount To Date $ 57,741.40
Reason For Change: Actual Field Quantities.
The time provided for completion of the contract is unchanged by 0 calendar days.
This document shall become an amendment to the contract and all provisions of the contract apply hereto.
Prepared by: Date:
Associate Engineer 11
Reviewed by: Date:
Wastewater Engineering Supervisor
Accepted by: Date:
Contractor's Representative
If this Change Order causes an increase from the original contract price, signed approval by the Director
constitutes representation that lawful appropriations are sufficient to cover such increase.
Approved by: Date:
Director of Wastewater
FORM C0100.1299
!e!(!(!(!(!(!(!(!(!e
484202.1484200.0484299.1
474299.0
484201.6
484103.2
484104.2
484102.8
484105.0
484104.1
484103.1
484104.5
484104.7
474102.7
!
e
!
(
!
(
!
(
!
(
!
!(
(
!
(
!
(
484108.4
!
(
474112.1484108.7
!
(
!
e
484112.5
474113.1
!
(
!
(
484117.0
!
(
Alley btn Cedar & Pine,
µ
Indiana-Minnequa
00.00705.0150.030.0450.06
Miles
City of Pueblo Wastewater Department
This map has been produced by the City of Pueblo, Wastewater Department, and is for reference only. Data provided herein is derived from sources with
varying levels of accuracy. The City of Pueblo disclaims all responsibility for the accuracy or completeness of the information contained herein.