HomeMy WebLinkAbout12249RESOLUTION NO. 12249
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT
IN THE AMOUNT OF $314,635.45 TO SHISLER, INC., AND
SETTING FORTH $40,000 FOR CONTINGENCIES AND
ADDITIONAL WORK, FOR PROJECT NO. 11-079 CITY PARK
SHELTER PROJECT AND AUTHORIZING THE PURCHASING
AGENT TO EXECUTE THE SAME
WHEREAS, proposals for PROJECT NO. 11-079 CITY PARK SHELTER PROJECT
have been received and examined, and;
WHEREAS, the proposal of Shisler, Inc. of Pueblo, Colorado, was the lowest of those
bids determined to be responsible;
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract for PROJECT NO.11-079 CITY PARK SHELTER PROJECT is hereby
awarded to said bidder in the amount of $314,635.45.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount
as stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work . . . . .$40,000
SECTION 4.
Funds for said project shall be from Project Code PL1004 – City Park Shelter
Enhancement.
INTRODUCED October 24, 2011
BY: Judy Weaver
COUNCILPERSON
Background Paper for Proposed
R
ESOLUTION
# M-3
DATE: OCTOBER 24, 2011 AGENDA ITEM
DEPARTMENT:
PUBLIC WORKS
DIRECTOR- EARL WILKINSON, P.E.
PARKS & RECREATION DEPARTMENT
DIRECTOR – CREIGHTON WRIGHT
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$314,635.45 TO SHISLER, INC., AND SETTING FORTH $40,000 FOR CONTINGENCIES
AND ADDITIONAL WORK, FOR PROJECT NO. 11-079 CITY PARK SHELTER PROJECT
AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
ISSUE
Should City Council award a construction contract for the CITY PARK SHELTER PROJECT to
Shisler Inc., for $314,635.45
RECOMMENDATION
Approval of this Resolution.
BACKGROUND
This project is located in City Park in the area between the kiddie rides and the existing
playground, north of the zoo parking lot. The base bid includes removal and replacement of
curb and gutter on the north side of the existing parking lot, removal of existing concrete
sidewalk, construction of 4”, 6” and 8” thick concrete sidewalk, installation of one 50’ octagon
shelter, four 12’ x 12’ shelters and breeze gravel. Add alternate bid items include installation of
electrical conduits for future lighting of the shelters, construction of curb head border and breeze
gravel, installation of swing sets with safety surface, picnic tables, benches and construction of
2’ wide colored concrete border.
Attached is a bid summary showing the result of competitive bids on this project.
FINANCIAL IMPACT
Funds for this project will be paid from Project Code PL1004– City Park Shelter Enhancement.