RESOLUTION NO. 12081
A RESOLUTION AWARDING A CONSTRUCTION
CONTRACT IN THE AMOUNT OF $14,495 TO PARKER
EXCAVATING, INC., FOR SANITARY SEWER POINT
REPAIR ON MARION DRIVE, AND AUTHORIZING THE
PURCHASING AGENT TO EXECUTE THE SAME
WHEREAS, an emergency sanitary sewer repair was authorized by the Pueblo City
Manager in accordance with Section 1-10-5 of the Pueblo Municipal Code, and;
WHEREAS the emergency repair work was awarded to Parker Excavating, Inc.
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract to repair the sanitary sewer on Marion Drive, Contract Agreement for Sanitary
Sewer Repair with Parker Excavating, Inc. (Project No. 09-002; WWAN01) and the same is
hereby awarded to said bidder in the amount of $14,495.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
Funds for said project shall be from the Sewer User Fund.
INTRODUCED: February 14, 2011
BY: Leroy Garcia
Background Paper for Proposed
RESOLUTION
AGENDA ITEM # M-4
DATE: FEBRUARY 14, 2011
DEPARTMENT: WASTEWATER DEPARTMENT
GENE MICHAEL, DIRECTOR
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$14,495 TO PARKER EXCAVATING, INC., FOR SANITARY SEWER POINT REPAIR
ON MARION DRIVE, AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE
THE SAME
ISSUE
Should the City Council award a construction contract in the amount of $14,495 to
Parker Excavating, Inc., for emergency sanitary sewer repair on Marion Drive?
RECOMMENDATION
Approve this Resolution.
BACKGROUND
A problem was discovered as a result of a sanitary sewer overflow that occurred on
January 18, 2011. The sewer main was found to be crushed, and TV inspection
showed debris stuck in the line causing blockages. The proximity to the river required
that it be rehabilitated immediately to prevent spills into waters of the State. Excavation
of the line was required.The quote for the unit prices for the work by Parker
Excavating, Inc. is attached. This work was done as an emergency under the Sanitary
Sewer Point Repair multi-year contract under which six contractors were qualified via
competitive bid.
During the project the costs were modified by actual field quantities as noted on the
attached change order.
The cost breakdown for the project is as follows:
Sewer Replacement-related
R&R 8” VCP to PVC..........................................$8,100.00
48” Manholes....................................................$3,995.00
Bypass Pumping...............................................$1,200.00
Mobilization.......................................................$1,200.00
Subtotal:..............$14,495.00 (100%)
Surface Improvement-related
None
TOTAL:................$14,495.00
FINANCIAL IMPACT
Funding for this project will come from the sanitary sewer rehabilitation budget funded
by the Sewer User Fund. Funding is available, and has been appropriated and
allocated to Project No. 09-002 (WWAN01).
CONTRACT AGREEMENT
For
Emergency Sanitary Sewer Repair
THIS AGREEMENT made and entered into this 21 day of January, 2011, by and between the City if
Pueblo, a Municipal Corporation, hereinafter referred to in the Contract Documents as the "City ", and Park. r
Excavating, Inc., referred to in the Contract Documents as "Contractor "
WITNESSETH In consideration of the sum to be paid by the City to the Contractor at the time and in the
manner hereinafter provided, the said Contractor has agreed, and does hereby agree, to furnish all labor,
tools, equipment and material and to pay for all such items, and to construct complete in every detail, To -Wit:
Project No 09 -002 (WWAN01)
FY2009 and 2010 Sanitary Sewer Point Repair
Sanitary Sewer Point Repair at Marion Drive
At the prices bid in Article 1 B Request for Quotation form, in accordance with the drawings and
specifications, and all Contract Documents for this project which are on file and available for inspection in thie
office of the Director of Wastewater, all to the satisfaction of the Director of Public Works for the City f
Pueblo, Colorado
AND FOR SAID CONSIDERATION IT IS FURTHER AGREED BY AND BETWEEN THE PARTIES T
THIS AGREEMENT AS FOLLOWS
1 Construction and installation of the above enumerated work for the City shall be completed and rea y
for use in accordance with the time of completion described in the Notice to Proceed for the Su -
Project. This time shall be extended only for those periods set forth in the Contract Documents an
in accordance with the requirements of same
2 The work and material for the Project covered by the Contract Documents shall be complete)
installed and delivered to the City within the time above stated, clear and free from any and all lien ,
claims and demands of any kind Wherever in the Contract Documents the term "Project" is used, it
shall be taken to mean this Sub - project.
3 The full compensation to be paid to the Contractor by the City, pursuant to the terms of this Contract,
shall be payable as provided in the Contract Documents
4 This Contract consists of the following component parts and documents, all of which taken togeth r
constitute and are referred to as the Contract Documents, and the same are incorporated as part f
the Contract as if set out herein verbatim, whether the same have been attached hereto or not:
A. Request for Quotations
B This Contract Agreement
C General Conditions of the Contract — Article 3
D Special Conditions
E The Standard Construction Specifications and Stands
Details for City of Pueblo, Colorado, (most current edition in
effect on date of bid opening), are hereby included by
reference and all provisions thereof shall be applicable By
submitting his bid, the Contractor acknowledges that he
possesses a copy of said document.
ARTICLE 1
B. REQUEST FOR QUOTATIONS
PROJECT NO 09 -002 (WWAN01)
PROJECT NAME Point Repair — Marion Drive
All proposals are to be prepared on this form All blank spaces must be correctly filled in whe -
indicated for each and every item for which a quantity is given, and the bidder must state the prices
(written in ink or typewritten) for which he proposes to do each item of the work contemplated or furnish
each item of the materials required
The undersigned, having become familiar with the local conditions affecting the cost of th-
work, and with the contract documents, including advertisement for bids, the form of proposal, the for
of contract, form of bond, special provisions of the contract, general provisions of the contract, etc ,
plans, drawings and specifications, issued and attached to the contract documents on file in the offic-
of the Purchasing Agent, hereby proposes to furnish all of the labor, materials, necessary tools an.
equipment and all utility and transportation service necessary to perform and complete in
workmanlike manner all of the work required in connection with the construction of an Emergen•
Repair on Marion Drive in accordance with the plans and specifications as prepared by or for the Ci
of Pueblo, Colorado, for the sums set forth in the following bidding schedule
BID ESTIMATED UNIT
ITEM DESCRIPTION QUANTITY PRICE AMOUNT
Marion Drive to the Arkansas River
1 Remove & Replace 8" PVC 300 LF $ 45 00 $ 13,500 00
2 Remove & Replace 48" Manholes 1 Each $ 3,995 00 $ 3,995 00
3 Mobilization 1 LS $ 1,200 00 $ 1,200 00
4 Bypass Pumping 1 LS $ 1,200 00 $ 1,200 00
GRAND TOTAL BID $ 19,895.00
(Nineteen thousand eight hundred and ninety -five dollars and zero cents)
The Grand Total Bid shall be the basis for establishing the amount of the performance bond f• r
this contract. The total bid is based on quantities shown on the proposal form and on the dimension
shown on the plans, and is subject to additions or reductions according to the actual constructio
quantities as determined by the Engineer upon completion of the construction
The City reserves the right to adjust the required quantities and the contractor shall furnish sai
quantities at the unit price quoted above The time allowed for construction shall be adjusted in dire t
proportion of the adjusted quantities to the estimated quantities.
The undersigned has carefully checked the above quantities against the plans and specification
before preparing this proposal and accepts the said quantities as substantially correct, both as to
classification and amount, and as correctly listing the work to be done in accordance with the plans an
specifications.
Page 1 of 2
C- ART1 -8; 1 -13 -2003
The bidder must sign his proposal correctly and in ink, if the proposal is offered by an individua ,
his name, office and post office address must be shown If made by a firm or partnership, the nam I ,
office and post office address of each member of the firm or partnership must be given, if offered by
corporation, the person signing the proposal must give the name of the state under the laws of whic
the corporation was chartered and the name, title and business address of the President, Secreta
and the Treasurer Anyone signing a proposal as agent must file legal evidence of his authority to d
so, and that the signature is binding upon the firm or corporation
The undersigned, if awarded the contract, agrees to complete and file the complete contract an
performance bond in quadruplicate within ten (10) days of the date of Notice of Award, and further
agrees to complete the work within thirty -five (35) calendar days of Notice to Proceed
Liquidated damages will be assessed in accordance with Section 3 54 of ARTICLE 3 -
GENERAL PROVISIONS, for every calendar day thereafter until the work is complete and accepted by
the City of Pueblo
NOTE Bidders should not add any conditions or qualifying statements to this bid as
otherwise the bid may be declared irregular as being not responsive to the
advertisement for bids
The contractor shall be subject to all applicable City County, State and
Federal Taxes in the performance of this contract.
Firm Name IL" 1r Xcl�.. 1 h C =Y1 L
Business Address ) q , 5 4rnc (. rJ
P . V . C- Sldal
By
Title
47
Date ` . — 1 / Tele No A 7/9 Sys 3e2
Fax No / 71 1 �S� - -e)r`j 5
Contractor's Federal I D Number d 7 0 �yr%,
Page 2 of 2
C-ART1-B; 1-13-2003
CONTRACT CHANGE ORDER
CITY OF PUEBLO DEPARTMENT OF PUBLIC WORKS
Project Number 09 -002 Change Order No. ONE 2/1/2011 Page 1 of 1
Project Name SANITARY SEWER POINT REPAIR MARION DRIVE
Contractor PARKER EXCAVATING INC
You are hereby requested to comply with the following changes from the plans & specifications.
Bid Item Description of Changes Decrease Increase
No Contract By Contract By
1 R &R 8' PVC < 8" ($5 400 00)
( TOTAL (Decrease) / Increase 11 ($5,400 00)11 $0 001
Net Adjustment This Change Order $ (5 400 00)
Amount of Previous Change Order(s) $ 0 00
Original Contract Amount $ 19 895 00
Total Adjusted Contract Amount To Date $ 14 495 00
Reason For Change Actual Field Quantities
Extra work needed to complete project
The time provided for completion of the contract is unchangec by 0 calendar days
This document shall become an amendment to the contract and all provisions of the contract apply hereto
Prepared by Date:
Associate Engineer 11
Reviewed by Date:
Wastewater Engineering Supervisor
Accepted by Date
Contractor's Representative
If this Change Order causes an increase from the original contract price, signed approval by the Director
constitutes representation that lawful appropriations are sufficient to cover such increase.
Approved by Date
Director of Wastewater
FORM C0100.1299