HomeMy WebLinkAbout11701RESOLUTION NO. 11701
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $369,028.00 TO SPACCAMONTI EXCAVATING, INC., AND
SETTING FORTH $73,806.00 FOR CONTINGENCIES, FOR THE FY2009
SANITARY SEWER REHABILITATION #2 PROJECT AND AUTHORIZING
THE PURCHASING AGENT TO EXECUTE THE SAME
WHEREAS, competitive bids for the Project No. 09 -082 FY2009 Sanitary Sewer
Rehabilitation #2 have been received and examined, and;
WHEREAS the proposal of Spaccamonti Excavating Inc. of Pueblo, Colorado was the
lowest of those bids determined to be responsive;
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract to replace the sanitary sewer at seven sites specified in the drawings,
Contract Agreement for Sanitary Sewer Repair with Spaccamonti Excavating Inc. (Project No.
09 -082; WWAN01) be, and the same is hereby awarded to said bidder in the amount of
$369,028.00.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
A Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount
as stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work ......... $73,806.00
SECTION 4.
Funds for said project shall be from the Sewer User Fund.
A77ESTED SY:
CITY CLERK
INTRODUCED: September 28, 2009
BY: Michael Occhiato
COUNCILPERSON
APPR t)' 40 �-
PRESIDENTof City Council
L) 4
Background Paper for Proposed
RESOLUTION
AGENDA ITEM # M -1
DATE: September 28, 2009
DEPARTMENT: WASTEWATER DEPARTMENT
GENE MICHAEL, DIRECTOR
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$369,028.00 TO SPACCAMONTI EXCAVATING, INC., AND SETTING FORTH
$73,806.00 FOR CONTINGENCIES, FOR THE FY2009 SANITARY SEWER
REHABILITATION #2 PROJECT AND AUTHORIZING THE PURCHASING AGENT TO
EXECUTE THE SAME
ISSUE
Should the City Council award a construction contract in the amount of $369,028.00 to
Spaccamonti Excavating, Inc., for the FY2009 Sanitary Sewer Rehabilitation #2
Project?
Approve this Resolution.
BACKGROUND
The City of Pueblo's Wastewater Department maintains a priority list for deteriorating
sewer mains that are discovered during the ongoing TV inspection process. The seven
sites chosen from the priority checklist for this project require rehabilitation. The sewer
mains at these sites range from 50 to 100 years in age, are made of vitrified clay, and
are showing major signs of deterioration. The deterioration includes severe
deformation, sags, and holes in the pipe. It is very important that these mains be
rehabilitated to protect the public's health and safety. A bid summary sheet is attached.
The cost breakdown for the project is as follows:
Sewer Replacement - related
Sewer Pipe Replacement ...............................
$147,922.00
Manhole Replacement ....... ...............................
$64,320.00
SS Service Reinstatement . ...............................
$23,100.00
Flowfill ................................... ...............................
$4,800.00
Bypass pumping ................... ...............................
$7,250.00
Traffic control ........................ ...............................
$3,950.00
Mobilization ........................... ...............................
$7,000.00
Subtotal ............. $258,342.00(70 %)
Surface Improvement - related
Concrete Work .................... ............................... $10,318.00
Curb & Gutter ........................ ............................... $6,027.00
Asphalt Patch and Paving .. ............................... $88,281.00
Miscellaneous Surface Improvements ............... $6,060.00
Subtotal .............$110,686.00 (30%)
TOTAL: $369,028.00
FINANCIAL IMPACT
Funding for this project will be taken from the Sewer User Fund. Funding is available
and was appropriated in the 2009 budget (Project No. 09 -082; WWAN01).
City of Pueblo Bid Summary Page I of 3
Project - No - -- 09 - -082 - ( - WWAN01)
DATE: 09109109 --- TIME - 10.00.00AM
-- -- ----
COMMODITY: FY2009 Sanitary Sewer Rehabilitation #2
Niebur Golf, Inc.
K.R. Swerdfeger
Construction, Inc.
Spaccamonti
Excavating, Inc.
Wildcat
Construction Co.
Inc.
ITEM DESCRIPTION Estimated Quantity
nit Price
1 iRemove and Replace 8" PVC 461 LF
Amount
45 00
$ 20,745.00
55.00
$ 25,355.00
42 50
- ------
$ 19,592.50
49 00
$ 22,589.00
' Unit Price
2 Reinstate Services 18 Each
_ 475.00
350.00
300.0 0
350.00
Amount
$ 8,550.00
$ 6,300.00
$ 5,400,00
$ 6,300.00
3 !Remove and Replace 48" MH
Unit Price
I Each
1 Amount
3500.00
2800.00
3560.00
3000.00
$ 3,500.00
$ 2,800.00
$ 3,560.00
$ 3,000.00
4 4" Asphalt on 6" Gravel Base
Unit Price
24 LF
45.00
67.00
45.00
53.00
; Remove and Replace 7"
5
Reinforced Concrete
mount
200 LS Unit Price
Amount_
$ 1,080.00
8.25
$ 1,608.00
8.00
$ 1,080.00
7.00
$ 1,272.00
15.00
$ 1,650.00
$ 1,600.00
$ 1,400.00
$ 3,000.00
Remove and Replace Standard
6
' Curb & Gutter
7 Bypass Pumping
8 ;Traffic Control
27 Unit Price
LF
Amount
Unit Price
1 LS
Amount
1 LS Unit Price
Amount
--
22.00
--
21.00
-- -
50.00
----
$ 540.00
4000.00
$ 4,000.00
1250.00
$ 594.00
1000.00
- ------
$ 1,000.00
500.00
$ 567.00
750.00
--
$ 750.00
300.00
$ 1,350.00
500.00
$ 500.00
400.00
$ 1,250.00
$ 500.00
$ 300.00
$ 400.00
9 'Mobilization
Unit Price
I LS
4500.00
2000.00
1000.00
2000.00
mount
$ 4,500.00,$
2,000.00,$
1,000.00
$ 2,000.00
Subtotal Site 1
Unit Price
10 Remove and Replace 8" PVC 450 LF I ----
Amount
:-4 Unit Price
! Reinstate Each I
$45,815.00
IM �Mll-
45.00
$41,757.00
65.00
$33,649.50
45.50
$40,411.00
tii4 49.00
- -- -
$ 20,250.00
475.00
-
$ 29,250.00
350.00
$ 20,475.00
300.00
$ 22,050.00
350.00
11 Services 18 ---
1 rAmount
$ 8,550.00
$ 6,300.00
$ 5,400.00
$ 6,300.00
Unit Price
!Remove MH I Each
2600.00
2800.00
3560.00
3000,00
12 and Replace 48"
Amount
$ 2,600.00
$ 2,800.00
$ 3,560.00
$ 3,000.00
---------- -
Unit Price
1 13 Construct Drop Manhole i I Each
i L-1 Amount
3000.00
3600.00
5780.00
4500.00
$ 3,000.00
$ 3,600.00
$ 5, 780.00
$ 4,500.00
Unit Price
14 Flowtill 10 CY
Amount
225.00
100.00
120.00
250.00
$ 2,250.00
$ 1,000.00
$ 1,200.00
$ 2,500.00
i j j Unit Price
15 4" Asphalt on 6" Gravel Base 1225 LF I -
a 'Amount
45.00
38.00
45.00
30.00
$ 55,125.00
-- ----
$ 46,550.00
- --
$ 55,125.00
--
$ 36,750.00
Unit Price
16 ;Reinforced Standard Double 156 k SF
--- Gzutter FA
8.25
-- ------- --------
8.00
8.00
38.00
$ 1,287.00
$ 1,248.00
$ 1,248.00
$ 5,928.00
lRemove and Replace 7" Unit Price
1 17 1 1 400 SF
Reinforced Concrete Amount
8.25
$ 3,300.00
8.00
$ 3,200.00
7.00
$ 2,800.00
15.00
$ 6,000.00
!Remove and Replace Standard Unit Price
18 50 LF
'Curb & Gutter I Amount
20.00
22.00
21.00
50.00
$ 1,000,00
$ 1,100.00
$ 1,050.00
$ 2,500.00
Unit Price
19 !Bypass Pumping I LS
Amount
4250.00
$ 4,250.00
1000.00
$ 1,000.00
750.00
$ 750.00
500.00
-
$ 500.00
20 !Traffic Control 1 LS _._Unit Price
Amount
1500.00
600.00
300.00
600.00
$ 1,500.00
$ 600.00
$ 300.00
$ 600.00
Unit Price
21 'Mobilization 1 LS
Amount
2500.00
$ 2,M O.010
2000.00
$ 2,000.00
1000.00
$ 1,000.00
2000.00
$ 2,000.00
Subtotal Site 2
$105,612.00
$98,648.00
$98,688.00
$92,628.00
- MIM11-12M
M�61-
M111W-411MV110M
WIWQ;10�11
j Unit Price
22 'Remove and Replace 8" PVC 282 1 1 LF
Amount
45.00
190.00
47.00
. .......... 49.00
$ 12,690.00
$ 53,580.00
$ 13,254.00
$ 13,818.00
Unit Price
i 23 !Reinstate Services 11 Each
Amount
475.00
$ 5,225.00
350.00
$ 3,850.00
300.00
$ 3,300.00
350.00
$ 3,850.00
Unit Price
24 ! Remove and Replace 48" MH i I Each
Amount
2600.00
$ 2,600.00
2800.00
$ 2,800.00
3560.00
$ 3,560.00
3000.00
$ 3,000.00
- - ------- -
f I Unit Price
25 Remove and Replace 60" MH I Each
Amount
3000-00
$ 3,000.00
3200.00
$ 3,200.00
4760.00
----
$ 4,760.00
3900.00
-- - -- - - - -- - -
$ 3,900.00
Unit Price
26 16"Asphalt on 6" Gravel Base 248 LF
i Amount
52.50
$ 13,020.00
75.00
$ 18,600.00
52.00
$ 12,896.00
7.00
$ 210.00
21.00
$ 2,310.00
46.00
$ 11,408.00
1500
Remove and Replace 7" Unit Price
27 30 SF
!Reinforced Concrete Amount
. Remove and Replace Standard 1 Unit Price
28 1 110 LF
Curb & Gutter Amount
8.25
247.50
20.00
$ 2,200.00
8.00
$ 240.00
22.00
$ 2,420.00
All prices as submitted -- Evaluation Committee will determine if bidder has met bid requirements.
uity of FueDio 13id bummary Page 2 of 3
Project No.: 09-082 (WWAN01)
Niebur Golf, Inc.
K.R. Swerdfeger
Construction, Inc.
Spaccamonti
Excavating, Inc.
Wildcat
Construction Co.
Inc.
DATE: 09/09/09 TIME: 10:00:00 AM
COMMODITY: FY2009 Sanitary Sewer
Rehabilitation
#2
'
29 Island Landscaping
1
Each
Unit Price
2500.00
5500.00
1550.00
7500.00
$ 1,550.00
$ 7,500.00
Amount
$ 2,500.00
$ 5,500.00
30 Bypass Pumping
I
LS
Unit Price
4000.00
---
1000.00
---
750.00
500.00
I Amount
$ 4,000.00
$ 1,000.00
$ 750.00
$ 500.00
31 'Traffic Control
1
LS
Unit Price
Amount
1500.00
$ 1,500.00
500.00
$ 500.00
300.00
$ 300.00
400.00
$ 400.00
32 !Mobilization
1
LS
Un
Unit Price
2250.00
2000.00
1000.00
2000.00
Amount
-
1 $ 2,250.001$
2,000.001$
1,000.001$
2,000.00
Subtotal Site 3
$49,232.50
$93,690.00
$43,890.00
$50,676.00
33 Remove and Replace 8" PVC 333 i LF t Price t
I m.0
A n
45.00
60.00
42.50
49.00
$ 14,985.00
$ 19,980.00
$ 14,152.50
$ 16,317.00
34 Reinstate Services
0
Each
Unit Price
r
0.00
0.00
0.00
350.00
-- - ----
Amount
$ -
35 (Remove and Replace 48" MH
2
Each
Unit Price
2600.00
----
2800.00
3560-00
3000.00
Amount
$ 5,200.00
$ 5,600.00
$ 7,120.00
$ 6,000.00
36 Flowfill
20
CY
Unit Price
225.00
100.00
120.00
250.00
Amount
Unit Price
$ 4,500.00
45.00
$ 2,000.00
72.0
$ 2,400.00
45.00
$ 5,000.00
40.00
37 14" Asphalt on 6" Gravel Base
i I
!Remove and Replace 7"
38
!Reinforced Concrete
340
40 I
LF
SF
Amount
Unit Price
$ 15,300.00
8.25
----.72.00
- --
$ 24,480.00
8.00
$ 15,300.00
7.00
- - - - -
$ 13,600.00
20.00
Amount
330.00
-
$ 320.00
$ 280.00
$ 800.00
39 Bypass Pumping i
I
'
LS
Und Price L P' e
5000.00
1000.00
750.00
500.00
Amount
$ 5,000.00
$ 1,000.00
$ 750.00
$ 500.00
40 !Traffic Control------7
I
L S
Unit Price
L
1750.00
800.001
500.001
Amount
Unit Price
$ 1,750.00
2250.00
$ 800.00
2000.00
$ 500.00
1000.00
--------500.00
500.00
2000.00
1 Mobilization
1
LS
Amount
$ 2,250.00
-
.00
$ 2,0001$
1,000.001$
2,000.00
Subtotal Site
4
$49,315.00
$56,180.00
$41,502.50
$",717.00
7 =nce
�PMMWMI �-TVV W I
9
42
43
!Remove and Replace 8" PVC
jReinstate Services I
487
13
LF
Each
=5nit
45.00
50.00
62.00
49.00
Amount
Unit Price
Amount
$ 21,915.00
475.00
-
$ 6,175.00
$ 24,350.00
350.00
$ 4,550.00
$ 30,194.00
300.00
$ 3,900.00
$ 23,863.00
350.00
$ 4,550.00
44
Remove and Replace 48" MH
3
Each
Unit Price
2600.00
2800.00
4560.00
3000.00
Amount
$ 7,800.00
$ 8,400.00
$ 13,680.00
$ 9,000.00
45
46
!Flowfill
' Asphalt on 6" Gravel Base
10
40
CY
LF
Unit Price
Amount
Unit Price
225.00
$ 2,250.00
52.50
100.00
$ 1,000.00
78.00
120.00
$ 1 , 200.00
52.00
250.00
$ 2 ,500.00
50.00
Amount
$ 2,100.00
$ 3,120.00
$ 2,080.00
$ 2,000.00
1 O i 47
U)
48
49
Remove Concrete
Construct Standard Alley
Approach
Remove and Replace Standard
Curb & Gutter
160
I
400
60
SF
I
SF
LF
Unit Price
5.00
1.00
3.00
25.00
Amount
Unit Price
$ 800-00
8.50
$ 160.00
8.00
$ 480.00
6.50
$ 4,000.00
15.00
--- ----- ---- -
rAmount
Unit Price
Amount
$ 3,400.00
20.00
$ 1,200.00
$ 3,200.00
22.00
$ 1,320.00
- $ 2.600.00
21.00
$ 1,260.00
$ - 6,000.00
50.00
$ 3,000.00
i 50
;Bypass Pumping
1
LS
Unit Price
10000.00
1000.00
1500.00
500.00
I Amount
$ 10,000.00
$ 1,000.00
$ 1,500.00
$ 500.00
Traffic Control
I
LS
Unit Price
2500.00
350.00
1550.00
550.00
--- ---
Amount
$ 2,500.00
$ 350.00
$ 1,550.00
$ 550.00
52
Mobilization
1
LS
I
I Unit Price
2250.00
2000.00
1000.001
2000.00
- - ---- ----
--
[Amount
--
$ 2,250.00
-- --- - -
i 2,000.00
$ 1,000.00
$ 2,000.00
Subtotal Site 5
Unit Price
53 ;Remove and Replace 8" PVC 1 427 LF
Amount
$60,390.00
45.00
$49,450.00
58.00
$59,444.00
62.00
$57,963.00
49.00
- -
$ 19,215.00
$ 24,766.00
I$s
$ 26,474.00
$ 20,923.00
54 !Reinstate Services 10
Each
Unit Price
475.00
350.00
300.00
350.00
Amount
$ 4,750.00
3,500.00
$ 3,000.00
$ 3,500.00
55 ' Remove and Replace 48" MH 2
i
56 !4" Asphalt on 6" Gravel Base 40
i
Each
LF
Unit Price
Amount
Unit Price
2600.00
$ 5,200.00
45.00
2800.00
$ 5,600.00
70.00
$--- 2.8
3560.00
$ 7,120.00
45.00
$ 1,800.00
3000.00
$ 6,000.00
42.00
$ 1,680.00
I Amount
$ -1,800.00-
All prices as submitted-Evaluation Committee will determine if bidder has met bid requirements.
City of Pueblo Bid Summary Page 3 of 3
Project No.: 09-082 (WWAN01)
DATE: 09/09/09 TIME: 10:00:00 AM
------- --
COMMODITY: FY2009 Sanitary Sewer Rehabilitation #2
Niebur Golf, Inc.
K R Swerdfeger
* '
Construction, Inc.
Spaccamonti
Excavating, Inc.
Wildcat
Construction Co.
Inc.
----------- ---------
lConstruct Standard Alley 1
57 Approach 200 SF
8.25
8.00
6.50
15.00
$ 1,650.00
$ 1,600.00
$ 1,300.00
$ 3,000.00
58
Remove and Replace Standard
40
Curb & Gutter
�iAmount
Unit Price
20.00
22.00
21.00
50.00
Amount
$ 800.00
$ 880.00
$ 840.00
$ 2,000.00
59
Bypass Pumping I
LS
Unit Price
Amount
5500.00
$ 5,500.00
1000.00
$ 1,000.00
1250.00
$ 1,250.00
500.00
$ 500.00
60
' Traffic Control 1
LS
Unit Price
2000.00
400.00
500.00
400.00
I Amount
$ 2,000.00
$ 400.00
$ 500.00
$ 400.00
61
Mobilization 1
LS
Unit Price
2250.00
2000.
1000.00
2000.00
Amount
$ 2,250.00
$ 2,000.001
1.000.001$
2,000.00
Subtotal Site
6
Unit Price
$43,165.00
45.00
$42,546.00
160.00
$43,284.00
58.00
$40,003.00
49.00
62 Remove and Replace 8" PVC
410
LF
Amount
$ 18,450.00
$ 65,600.00
$ 23,780.00
-- - - --
$ 20,090.00
63 'Reinstate Services
I
7
Each
Unit Price
Amount
550.00
$ 3,850.00
350.00
$ 2,450.00
300.00
$ 2,100.00
350.00
$ 2,450.00
64 ;Remove and Replace 48" MH
I
6 Construct 48" MH
5
3
I
Each
Each
Unit rice
A mo u nt
Unit Price
Amount
3500,00
$ 10,500.00
_3000,00
$ 3,000.00
2800.00
-
$ 8,400.00
2700.00
$ 2,700.00
3560.00
$ 10,680.00
4500.00
$ 4,500.00
3000.00
$ 9,000.00
3000.00
$ 3,000.00
66 Rotomillings
200
SY
Unit Price
F
4.00
$ 800.00
8.00
$ 1,600.00
9.50
$ 1,900.00
11.00
$ 2,200.00
67 IReseeding
870
_7
SY
Unit Price
0.40
5.00
3.00
8.00
I Amount
$ 348.00
$ 4,350.00
$ 2,610.00
_$ 6,960.00
68 Bypass Pumping
1
LS
Unit Price
Amount
6500.00
$ 6,500.00
1000.00
$ 1,000.00
1500.00
$ 1,500.00
500.00
$ 500.00
69 !Traffi. Control
I
LS
Unit Price
1750.00
800.001
50000
800.00
Amount
$ 1,750.00
$ 800.00
$ 500.00
$ 800.00
70
LS
Unit Price
3250.00
2000.00
1$
1000.00
2000.00
Amount
$ 3,250.00
$ 2,000.0
1,000.001s
2,000.00
Subtotal Site 7
$48,448.00
$88,900.00
$48,570.00
$47,000.00
GRAND TOTAL BID
$401,977.50
$471,171.00
$369,028.00
$373,398.00
Mandatory Submittals
yes
yes
yes
yes
All prices as submitted--Evaluation Committee will determine if bidder has met bid requirements.