A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $272,900.00 TO WASHINGTON PIPELINE, LLC, AND
SETTING FORTH $54,580.00 FOR CONTINGENCIES, FOR THE FY2009
FORCE MAIN ISOLATION VALVES PROJECT AND AUTHORIZING THE
PURCHASING AGENT TO EXECUTE THE SAME
WHEREAS, competitive bids for the Project No. 09 -078 (WWAN01) FY2009
Force Main Isolation Valves have been received and examined, and;
WHEREAS the proposal of Washington Pipeline, LLC of Mercer Island, Washington was
the lowest of those bids determined to be responsive;
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO. that:
SECTION 1.
A contract to install 18 Force Main Isolation Valves at the Airport Industrial Park
specified in the drawings, Contract Agreement for Isolation Valve installation with Washington
Pipeline LLC (Project No. 09 -078; (WWAN01)) be, and the same is hereby awarded to said
bidder in the amount of $272,900.00.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
A Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount
as stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work ......... $54,580.00
SECTION 4.
Funds for said project shall be from the Sewer User Fund.
A77ESTED SY:
CITY CLERK
INTRODUCED: September 14, 2009
BY: Michael Occhiato
COUNCILPERSON
APPR t)' 40 �-
PRESIDENTof City Council
4
Background Paper for Proposed
RESOLUTION
AGENDA ITEM # M -1
DATE: September 14, 2009
DEPARTMENT: WASTEWATER DEPARTMENT
GENE MICHAEL, DIRECTOR
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$272,900.00 TO WASHINGTON PIPELINE, LLC, AND SETTING FORTH $54,580.00 FOR
CONTINGENCIES, FOR THE FY2009 FORCE MAIN ISOLATION VALVES PROJECT AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
ISSUE
Should the City Council award a construction contract in the amount of $272,900.00 to
Washington Pipeline LLC, for the FY2009 Force Main Isolation Valves Project?
RECOMMENDATION
Approve this Resolution
BACKGROUND
Wastewater service for the Pueblo Airport Industrial Park is provided via a series of sewer lift
stations and force mains. Currently, the Wastewater Department cannot inspect or maintain the
force main due to a design flaw that causes wastewater to flood the cleanout manholes and
causes safety issues for maintenance crews. Installation of 18 isolation valves would allow the
maintenance crew to regulate the flow in these manholes and resolve the safety issue, making
safe inspection and maintenance possible. A bid summary sheet is attached.
FINANCIAL IMPACT
Funding for this project will be taken from the Sewer User Fund. Funding is available and was
appropriated in the 2009 budget, Project No. 09 -078 (WWAN01).
City of Pueblo Bid Summary Page 1 of 1
Project: 09 -078 (VWNAN01)
Project Name: FY 2009 Force Main Isolation Spaccamonti K. R. A & R
Valves Washington Excavating, Swerdfeger Construction,
Pipeline,LLC Inc. Constrtuction, LLC
Inc.
DATE: 09/02/2009 TIME: 10:00:00 AM
ITEM DESCRIPTION Price
1 Install 18 Isolation Valves Grand Total Bid $ 272,900.00 $ 438,200.00 $ 293,220.00 $ 340,000.00
Mandatory Submittals) X I X I X I X
All prices as submitted -- Evaluation Committee will determine if bidder has met bid requirements.