HomeMy WebLinkAbout11447RESOLUTION NO. 11447
A RESOLUTION APPROVING AN APPLICATION FOR
INTERIM REMEDIATION AND CONSTRUCTION WORK UPON
THE PHASE III UNIT OF PUEBLO SOUTHSIDE LANDFILL
WHEREAS, on June 22, 1992, Council adopted Resolution No. 6951 which
ratified, approved and authorized a separate Certificate of Designation for municipal
solid waste landfill units identified as Phase II and Phase III of the Pueblo Southside
Landfill; and
WHEREAS, said Certificate of Designation for the Phase III Unit was effective
and the facility began operation prior to adoption of Ordinance 5996 of the City of
Pueblo, passed and approved on July 24, 1995; and
WHEREAS, on July 14, 1997, Council adopted Ordinance No. 6208 which
approved with conditions a major modification to said Certificate of Designation for the
Phase III Unit, Pueblo Southside Landfill, which modification had been requested by the
operator, Zupan Enterprises, Inc.; and
WHEREAS, on April 26, 2004, Council adopted Ordinance No. 7130 which
approved with conditions a major modification to said Certificate of Designation for the
addition of new liquid waste and sludge impoundments to the Phase III Unit, Pueblo
Southside Landfill, which modification had been requested by the operator Zupan
Enterprises, Inc.; and
WHEREAS, Zupan Enterprises, Inc., by its contractor Waste Connections of
Colorado, Inc. ( "WCI "), has now submitted an application for Interim Remediation and
Construction Work (the "Application "), a true copy of which is attached hereto, in order
to correct certain deficiencies observed in Phase III and to allow its subsequent
reopening and to obtain compliance with regulatory requirements; and
WHEREAS, the Application does not seek modification to the Certificate of
Designation subject to the provisions of Ordinance 5996, as codified in Chapter 12 of
Title IV of the Pueblo Municipal Code and of Part 1 of Article 20 of Title 30, Colorado
Revised Statutes, but rather, only seeks approval of temporary corrective modifications;
and
WHEREAS, the Application has been reviewed by the Colorado Department of
Public Health and Environment ( "CDPHE ") and CDPHE has indicated its concurrence
that the remediation and construction described in the Application should be performed;
NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1
The Application for approval of Interim Remediation and Construction Work upon
the Phase III Unit, as set forth in the Application, is hereby approved, and is found not to
constitute a major modification or minor modification to the Certificate of Designation for
the Phase III Unit facility.
SECTION 2
This Resolution shall become effective immediately upon final passage and
approval.
BY Judy Weaver
Councilperson
PRt
i I I T'�l rtw d]UH�
ATTESTED aY
{
CLERK
INTRODUCED October 14. 2008
AGENDA ITEM # 38A
DATE: October 14, 2008
DEPARTMENT: City Manager and Law Department
TITLE
A RESOLUTION APPROVING AN APPLICATION FOR INTERIM REMEDIATION AND
CONSTRUCTION WORK UPON THE PHASE III UNIT OF PUEBLO SOUTHSIDE
LANDFILL
ISSUE
Should Council approve an application on behalf of Zupan Enterprises, Inc. to perform
certain remediation and construction work at the Phase III Unit of the Southside
Landfill?
RECOMMENDATION
Approval is recommended in order that the solid waste disposal facility reopen at the
earliest possible time.
BACKGROUND
On July 28, City Council approved a transaction which essentially allowed Waste
Connections, Inc. ( "WCI ") to evaluate Phase II and III of the Pueblo Southside Landfill,
and authorized WCI to obtain approval to acquire Phase II and III from Zupan
Enterprises and subsequently reopen the Landfill upon specified terms.
As part of the evaluation process, certain remedial /corrective work has been identified
and may be performed prior to (a) the closing of the above - described transaction, and
(b) City action on modification of the Certificate of Designation for the Phase II and
Phase III Units. By allowing the remedial work to proceed on this basis, identified
problems with the facility will be corrected and the re- opening of the facility may logically
proceed without unnecessary delay. Approval of this Resolution is consistent with
protection of public health and safety.
FINANCIAL IMPACT
None.
VVIMAYER
BOOB
CON aXYZ1 `A1wre
Tarr
October 7, 2008
Project No. 0601 - 508- 11 -07 -01
Mr. Dave Galli, City Manager
City of Pueblo
I City Hall Place
Pueblo, CO 81003
Owner and Operator : Zupan Enterprises, Inc.
Application . Interim Remediation and Construction Work
Location Phase III at the Southside Landfill, Pueblo County
Contractor Waste Connections of Colorado, Inc..
Project Duration 4 to 6 weeks
Dear Mr.. Galli:
The purpose of this application, submitted on behalf of Zupan Enterprises, Inc., is to
request approval for an interim remediation and construction project that is planned at
the Southside Landfill. To facilitate the City's review of this request, a site plan is
attached The proposed remediation and construction work that will be performed for
the area is known as "Phase III" at the landfill_ This request includes Module A, as
shown on Drawing 1. Module B will be constructed at a later date. The proposed work
is summarized below..
• Perimeter Berm. A perimeter berm will be constructed in the area southeast of
Phase III. The perimeter berm will be constructed of compacted soil and tested
to verify that the project compaction specifications are met.
• Extension of Existing Lined Area As shown on Drawing 1, the existing liner
will be extended between the existing limits of waste and the top of'the perimeter
berm. The waste disposal area, or "landfill footprint," will be extended by this
construction project to allow the slopes of Phase III to be re- shaped to meet
applicable regulatory requirements.,
the remediation and construction work will be completed by Waste Connections of
Colorado, Inc. and their subcontractors on behalf' of Zupan Enterprises, Inc. The
remediation and construction work will begin upon receiving City approval of this
project. The duration of'this project should be about 4 to 6 weeks.
rorr¢azoarrsax(/.W c
Chicago, 11
Naperville, IL
5675 DT C Boulevard, Suite 210
G,iffith, IN
Greenwood Village, Colorado 80111
south Bend, IN
Phone. 720 - 529 -0132
Springfield, IL
St. Louis, MO
Fax: 720- 529 -0137
Colu,nbu% OH
www.weaverboos -Corn
port Worth TX
Denver, CO
Grand Rapids, MI
Orlando, H.
October 7, 2008
Project No. 0601 - 508- 11 -07 -01
Mr. Dave Galli, City Manager
City of Pueblo
I City Hall Place
Pueblo, CO 81003
Owner and Operator : Zupan Enterprises, Inc.
Application . Interim Remediation and Construction Work
Location Phase III at the Southside Landfill, Pueblo County
Contractor Waste Connections of Colorado, Inc..
Project Duration 4 to 6 weeks
Dear Mr.. Galli:
The purpose of this application, submitted on behalf of Zupan Enterprises, Inc., is to
request approval for an interim remediation and construction project that is planned at
the Southside Landfill. To facilitate the City's review of this request, a site plan is
attached The proposed remediation and construction work that will be performed for
the area is known as "Phase III" at the landfill_ This request includes Module A, as
shown on Drawing 1. Module B will be constructed at a later date. The proposed work
is summarized below..
• Perimeter Berm. A perimeter berm will be constructed in the area southeast of
Phase III. The perimeter berm will be constructed of compacted soil and tested
to verify that the project compaction specifications are met.
• Extension of Existing Lined Area As shown on Drawing 1, the existing liner
will be extended between the existing limits of waste and the top of'the perimeter
berm. The waste disposal area, or "landfill footprint," will be extended by this
construction project to allow the slopes of Phase III to be re- shaped to meet
applicable regulatory requirements.,
the remediation and construction work will be completed by Waste Connections of
Colorado, Inc. and their subcontractors on behalf' of Zupan Enterprises, Inc. The
remediation and construction work will begin upon receiving City approval of this
project. The duration of'this project should be about 4 to 6 weeks.
rorr¢azoarrsax(/.W c
I
Mr.. Dave Galli
October 7, 2008
Page 2
If you have any questions or require further information, please call.
Sincerely,
Weave Consultan LLC
SSA ---,
John Briest, PE
Senior Project Manager
Attachments: Drawing 1— Site Plan
Zupan Ente 7 ses, Inc.
Michael upan , P
Owner A