HomeMy WebLinkAbout11410RESOLUTION NO. 11410
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF $73,530.50
TO CEDAR RIDGE LANDSCAPE, INC., AND SETTING FORTH $26,469.50 FOR
CONTINGENCIES AND ADDITIONAL WORK, FOR PROJECT NO 08 -055 (CD0805) FY 2008
BESSEMER CROSSPAN REPLACEMENT (CDBG) PROJECT AND AUTHORIZING THE
PURCHASING AGENT TO EXECUTE THE SAME
WHEREAS, proposals for PROJECT NO. 08 -055 FY 2008 BESSEMER CROSSPAN
REPLACEMENT PROJECT have been received and examined, and;
WHEREAS, the proposal of CEDAR RIDGE LANDSCAPE, INC., of Pueblo, Colorado was
the lowest of those bids determined to be responsible;
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract for PROJECT NO. 08 -055 FY 2008 BESSEMER CROSSPAN REPLACEMENT
PROJECT be, and the same is hereby awarded to said bidder in the amount of $73,530.50.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo, A
Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount as
stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work .....$26,469.50
SECTION 4.
Funds for said project shall be from Project Code CD0805.
BY Randy Thurston
Councilperson
I`81f I T' i ILim
ATTEST D BY
INTRODUCED September 22, 2008
o �
0
Background Paper for Proposed
RESOLUTION
AGENDA ITEM #
DATE: SEPTEMBER 22, 2008
DEPARTMENT: PUBLIC WORKS
DIRECTOR- DANIEL E. CENTA, P.E.
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$73,530.50 TO CEDAR RIDGE LANDSCAPE, INC., AND SETTING FORTH $26,469.50 FOR
CONTINGENCIES AND ADDITIONAL WORK, FOR PROJECT NO. 08 -055 (CD0805) FY 2008
BESSEMER CROSSPAN REPLACEMENT (CDBG) PROJECT AND AUTHORIZING THE
PURCHASING AGENT TO EXECUTE THE SAME
ISSUE
Should City Council award a construction contract for FY 2008 BESSEMER CROSSPAN
REPLACEMENT PROJECT to CEDAR RIDGE LANDSCAPE, INC., for $73,530.50.
RECOMMENDATION
Approval of this Resolution
BACKGROUND
This project will remove and replace approximately 7 deteriorated concrete crosspans
and install new A.D.A. curb ramps on 12 street corners at various locations in the
Bessemer I Minnequa area.
See attached Exhibit "A" for the location of the project.
This project was funded for $100,000. Attached is a bid summary showing the result of
competitive bids on this project.
FINANCIAL IMPACT
Funds for this project will be paid from Community Development Block Grant Funds,
Project Code CD0805.
EXHIBIT "A"
FY 2008 Bessemer Crosspan Replacement (CD0805)
Division Ave. & Spruce St. — north side
Division Ave. & Spruce St. — south side
Division Ave. & Pine St. — north side
Jones Ave. & Pine St. — south side
Logan Ave. & Routt Ave. — west side
Logan Ave. & Cedar St. east side
Baystate Ave. & Cedar St. — south side