HomeMy WebLinkAbout11387RESOLUTION NO. 11387
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF $47,250.00
TO 144 CONSTRUCTION CORPORATION, AND SETTING FORTH $9,450.00 FOR
CONTINGENCIES, FOR RELOCATION OF THE SANITARY SEWER FOR THE PUEBLO
MUNICIPAL COMPLEX AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE
SAME
WHEREAS, a sanitary sewer relocation was authorized by the Pueblo City Manager in
accordance with Section 1 -10 -5 of the Pueblo Municipal Code, and;
WHEREAS the repair work was awarded to 144 Construction Corporation.
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract to relocate the sanitary sewer for the Pueblo Municipal Complex, Contract
Agreement for Sanitary Sewer Repair with 144 Construction Corporation. (Project No. 07 -007;
WW0808) be, and the same is hereby awarded to said bidder in the amount of $47,250.00.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo, A
Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount as
stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work......... $9,450.00
SECTION 4.
Funds for said project shall be from the Sewer User Fund.
INTRODUCED Auqust 25, 2008
BY Vera Ortegon
Councilperson
AP PROVE
ATTE D BY: �. � y
PRESS NT'ei Cif' Council
Background Paper for Proposed
RESOLUTION
AGENDA ITEM # 9J
DATE: AUGUST 25, 2008
DEPARTMENT: WASTEWATER DEPARTMENT
GENE MICHAEL, DIRECTOR
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $47,250.00 TO 144 CONSTRUCTION CORPORATION, AND
SETTING FORTH $9,450.00 FOR CONTINGENCIES, FOR RELOCATION OF
THE SANITARY SEWER FOR THE PUEBLO MUNICIPAL COMPLEX AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
ISSUE
Should the City Council award a construction contract in the amount of
$47,250.00 to 144 Construction Corporation for relocation of the sanitary sewer
for the Pueblo Municipal Complex.
RECOMMENDATION
Approve this Resolution.
BACKGROUND
In the latter portion of 2008 to 2009, the City of Pueblo will begin construction on
the new Pueblo Municipal Complex. The Wastewater Department must reroute
the existing sewer to accommodate the footprint of the Police /Municipal Court
building. 144 Construction Corporation was the lowest bidder on the "Approved
List", as established in Resolution No. 10968 on April 9, 2007 and was therefore
awarded this project.
The cost breakdown for the project is as follows:
Sewer Replacement- related
Manhole replacement .................
.....................$18,000.00
Bypass pumping ............ ...............................
Cost + 15%
Utility service restoration ...
............................... $4,800.00
Mobilization .......................
............................... $3,000.00
Sewer pipe replacement ...
............................... 21 450.00
TOTAL: ................ $47,250.00
FINANCIAL IMPACT
Funding for this project will come from the repair budget funded by the Sewer
User Fund. Funding is available and has been appropriated.