A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF $49,791.45
TO CORTEZ CONSTRUCTION CO., AND SETTING FORTH $15,208.55 FOR CONTINGENCIES
AND ADDITIONAL WORK, FOR PROJECT NO. 08 -060 (CD0714), FY 2008 MITCHELL PARK
PLAYGROUND EQUIPMENT AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE
THE SAME
WHEREAS, proposals for PROJECT NO. 08 -060 (CD0714), FY 2008 MITCHELL PARK
PLAYGROUND EQUIPMENT have been received and examined, and;
WHEREAS, the proposal of Cortez Construction Co., Pueblo, Colorado was the lowest of
those bids determined to be responsible;
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract for PROJECT NO. 08 -080 (CP0714), FY 2008 MITCHELL PARK
PLAYGROUND be, and the same is hereby awarded to said bidder in the amount of $49,791.45.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo, A
Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount as
stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work .......$ 15,208.55
SECTION 4.
Funds for said project shall be paid out of Project No. CD0714.
INTRODUCED June 23, 2008
BY Vera Ortegon
Councilperson
AP PROVE
ATTE D BY: �. � y
PRESS NT'ei Cif' Council
1 2 �-s II3�Z
r F --- = 0
� E
NMEW
Background Paper for Proposed
RESOLUTION (�
AGENDA ITEM # `{
DATE: JUNE 23, 2008
DEPARTMENT: PUBLIC WORKS
DIRECTOR — DANIEL E. CENTA, P.E.
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $49,791.45 TO CORTEZ CONSTRUCTION CO., AND SETTING
FORTH $15,208.55 FOR CONTINGENCIES AND ADDITIONAL WORK FOR
PROJECT NO. 08 -060 (CD0714), FY 2008 MITCHELL PARK PLAYGROUND
EQUIPMENT AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE
THE SAME
ISSUE
Should City Council award a construction contract for Project No. 08 -060
(CD0714), FY 2008 Mitchell Park Playground Equipment to CORTEZ
CONSTRUCTION CO. for $49,791.45.
RECOMMENDATION
Approval of this Resolution.
BACKGROUND
In general, this project will consist of the removal and disposal of the existing
playground equipment and safety surface and the furnishing and installation of
new ADA compliant play equipment and safety surface with drainage system at
the existing playground in Mitchell Park.
Attached is a bid summary showing the result of competitive bids on this project.
FINANCIAL IMPACT
Funding for this project will be paid out of Project CD0714.