A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$461,857.67 TO CORTEZ CONSTRUCTION CO., AND SETTING FORTH $69,278.65 FOR
CONTINGENCIES AND ADDITIONAL WORK, FOR PROJECT NO. 08 -007 (CP0713), FY 2008
MITCHELL SPRAY PARK AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE
SAME
WHEREAS, proposals for PROJECT NO. 08 -007 (CP0713), FY 2008 MITCHELL
SPRAY PARK have been received and examined, and;
WHEREAS, the proposal of Cortez Construction Co., Pueblo, Colorado was the lowest
of those bids determined to be responsible;
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1 _
A contract for PROJECT NO. 08 -007 (CP0713), FY 2008 MITCHELL SPRAY PARK be,
and the same is hereby awarded to said bidder in the amount of $461,857.67.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
A Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount
as stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work .......$ 69,278.65
SECTION 4.
Funds for said project shall be paid out of Project No. CP0713 from the following grant:
County 1A Ballot Initiative $750,000
BY Judy Weaver
Councilperson
I`81f I T' i ILA HL-
ATTEST D BY
INTRODUCED February 11, 2008
i
Background Paper for Proposed
RESOLUTION
AGENDA ITEM #
DATE: FEBRUARY 11, 2008
DEPARTMENT: PUBLIC WORKS
DIRECTOR — DANIEL E. CENTA, P.E.
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $461,857.67 TO CORTEZ CONSTRUCTION CO., AND SETTING
FORTH $69,278.65 FOR CONTINGENCIES AND ADDITIONAL WORK FOR
PROJECT NO. 08 -007 (CP0713), FY 2008 MITCHELL SPRAY PARK AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
ISSUE
Should City Council award a construction contract for Project No. 08 -007
(CP0713), FY 2008 Mitchell Spray Park to CORTEZ CONSTRUCTION CO. for
$461,857.67.
RECOMMENDATION
Approval of this Resolution.
BACKGROUND
In general, this project will consist of the construction of a re- circulating, treated
water spray park with ground -spray and surface - mounted water features,
equipment room, underground water holding tank, shade structures, 6' chain link
fence and concrete sidewalk as specified in the plans and the specifications.
FINANCIAL IMPACT
Funding for this project will be paid out of Project CP0713 from the following
grant:
County 1A Ballot Initiative $750,000
Attached is a bid summary showing the results of competitive bids on this project.