HomeMy WebLinkAbout11080RESOLUTION NO. 11080
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$180,000.00 TO K.R. SWERDFEGER CONSTRUCTION, INC., AND SETTING FORTH
$55,000.00 FOR CONTINGENCIES, FOR THE PENN AVENUE EMERGENCY SANITARY
SEWER REPAIR, AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
WHEREAS, an emergency sanitary sewer repair was authorized by the Pueblo City
Manager in accordance with Section 1 -10 -5 of the Pueblo Municipal Code, and;
Inc.
WHEREAS the emergency repair work was awarded to K.R. Swerdfeger Construction,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract to replace the sanitary sewer in Penn Avenue to the intersection with East
Corona Avenue, Contract Agreement for Sanitary Sewer Repair with K.R. Swerdfeger
Construction, Inc. (Project No. 07 -007; WW0701) be, and the same is hereby awarded to said
bidder in the amount of $180,000.00.
SECTION 2_
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo,
A Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3_
In addition to the amount of the bid set forth, as aforementioned, an additional amount
as stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work......... $55,000.00
SECTION 4.
Funds for said project shall be from the Sewer User Fund.
INTRODUCED Auaust 13. 2007
BY Randy Thurston
Councilperson
APPROVED: a u & " e -
#?ESIDEINTof City Council
ATTESTED BY:
CITY CLERK
Ve.5. IOS:O
Background Paper for Proposed
RESOLUTION
AGENDA ITEM # I I
DATE: AUGUST 13, 2007
DEPARTMENT: WASTEWATER DEPARTMENT
GENE MICHAEL, DIRECTOR
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE
AMOUNT OF $180,000.00 TO K.R. SWERDFEGER CONSTRUCTION, INC.,
AND SETTING FORTH $55,000.00 FOR CONTINGENCIES, FOR THE PENN
AVENUE EMERGENCY SANITARY SEWER REPAIR, AND AUTHORIZING
THE PURCHASING AGENT TO EXECUTE THE SAME
ISSUE
Should the City Council award a construction contract in the amount of $180,000
to K.R. Swerdfeger Construction, Inc., for the Penn Avenue emergency sanitary
sewer repair?
RECOMMENDATION
Approve this Resolution.
BACKGROUND
On Wednesday, July 11, 2007, the Wastewater Department became aware of a
blocked sanitary sewer line in Penn Avenue near the intersection with East
Corona Avenue. A cleaning hose became stuck in a 6 -inch sanitary sewer main
during routine maintenance. Efforts to extract the hose were unsuccessful. The
sewer main dates from 1928, and it was feared that more strenuous efforts to
remove the hose could cause the main to collapse. Because the existing sewer
main runs outside the paved street and buildings have been erected over
portions of the sewer main, it is necessary to construct a new main in a different
alignment to restore service. There are issues with underground utilities and
overhead electric poles that require equipment the City does not own. Because
the job proved to be beyond the scope of the Wastewater Department, the City
Manager was asked on July 11, 2007 to approve an emergency repair. A copy
of the agreement with K.R. Swerdfeger Construction, Inc. is attached, along with
the quote for the unit prices for the work.
FINANCIAL IMPACT
Funding for this project will come.from the emergency repair budget funded by
the Sewer User Fund. Funding is available and was appropriated in the 2007
budget.
CONTRACT AGREEMENT
For
Emergency Sanitary Sewer Repair
THIS AGREEMENT made and entered into this 27th day of July, 2007, by and between the City of
Pueblo, a Municipal Corporation, hereinafter referred to in the Contract Documents as the " City ", and K.R.
Swerdfeger Construction Inc., referred to in the Contract Documents as " Contractor ".
W ITNESSETH: Inconsideration of the sum to be paid by the City to the Contractor at the time and in the
manner hereinafter provided, the said Contractor has agreed, and does hereby agree, to furnish all labor,
tools, equipment and material and to pay for all such items, and to construct complete in every detail, To -Wit
Project No. 07 -007 (WW07 -01)
2007 and 2008 Emergency Sanitary Sewer Point Repair
Penn Avenue
At the prices bid in Article 1.6. Request for Quotation form, in accordance with the drawings and
specifications, and all Contract Documents for this project which are on file and available for inspection in the
office of the Director of Wastewater, all to the satisfaction of the Director of Public Works for the City of
Pueblo, Colorado
AND FOR SAID CONSIDERATION IT IS FURTHER AGREED BYAND BETWEEN THE PARTIES TO
THIS AGREEMENT AS FOLLOWS:
1. Construction and installation of the above enumerated work forthe City shall be completed and ready
for use in accordance with the time of completion described in the Notice to Proceed for the Sub -
Project. This time shall be extended only for those periods set forth in the Contract Documents and
in accordance with the requirements of same.
2. The work and material for the Project covered by the Contract Documents shall be completely
installed and delivered to the City within the time above stated, clear and free from any and all liens,
claims and demands of any kind. Wherever in the Contract Documents the term "Project' is used, it
shall be taken to mean this Sub - project.
3. The full compensation to be paid to the Contractor by the City, pursuant to the terms of this Contract,
shall be payable as provided in the Contract Documents.
4. This Contract consists of the following component parts and documents, all of which taken together
constitute and are referred to as the Contract Documents, and the same are incorporated as part of
the Contract as if set out herein verbatim, whether the same have been attached hereto or not:
A. Request for Quotations
B. This Contract Agreement
C. General Conditions of the Contract — Article 3
D. Special Conditions
E. The Standard Conahvctlon Speel6cadons and Standard
DetallaforCUTafpueblo, Colorado, (most current edition in
effect on date of bid opening), are hereby included by
reference and all provisions thereof shall be applicable. By
submitting his bid, the Contractor acknowledges that he
possesses a copy of said document.
5. Title XI I, Chapter 2, of the 1971 Code of Ordinances, City of Pueblo, adopted by Ordinance No. 3476,
and amended by Ordinance No. 4476 and 5229, shall be considered a part of this contract.
6. Title I, Chapter 8, of the 1971 Code of Ordinances, City of Pueblo, adopted by Ordinance No. 4479,
shall be considered a part of the contract.
7. All of the covenants and agreements set forth in the Contract Documents shall inure to the benefit of
and be binding upon City and Contractor and their respective heirs, legal successors and assigns
and shall be governed by the laws of the State of Colorado.
8. Payment and Performance Bonds will not be required for this project if the bid amount is less than
$50,000.00 (per §38 -26 -106, C.R.S.). Progress payments will not be made, and a single payment
all work will be made upon completion of the entire Project and verification is made that it has been
inspected and approved by authorized Wastewater personnel.
IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed in four (4)
original counterparts as of the day and year first above written.
PUEBLO, A MUNICIPAL CORPORATION
By `_ —�
Purchasing Agent
ATTEST:
City Clerk
BALANCE OF APPROPRIATION EXISTS FOR
THIS C T CT AND F UNDS ARq AVAILABLE:
Director of Finance
APPROVED AS TO FORM:
Ci mey
Titl J'(�Y