HomeMy WebLinkAbout10974RESOLUTION NO. 10974
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$659,741.00 TO T.L. PRINTZ CONSTRUCTORS AND SETTING FORTH $70,259.00 FOR
CONTINGENCIES AND ADDITIONAL WORK FOR PROJECT NO. 07 -014 FY 2007 ADA
ACCESSIBILITY IMPROVEMENTS EL CENTRO DEL QUINTO SOL RECREATION CENTER
AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
WHEREAS, proposals for the Project No. 07 -014 (CP0504) FY 2007 ADA Accessibility
Improvements El Centro del Quinto Sol Recreation Center have been received and examined, and;
WHEREAS, the proposal of T.L. Printz Constructors of Pueblo, Colorado was the lowest of
those bids determined to be responsible;
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract for the Project No. 07 -014 (CPO504) FY 2007 ADA Accessibility Improvements
El Centro Del Quinto Sol Recreation Center be, and the same is hereby awarded to said bidder in
the amount of $659,741.00.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo, A
Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount as
stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work .... $70,259.00
SECTION 4.
Funds for said project shall be from Project Codes CP0504
INTRODUCED April 9, 2007
BY Randy Thurston
Councilperson
APPROVED:
RRESIDIENTof City Council
ATTESTED BY:
CITY CLERK
12ES i
Background Paper for Proposed
RESOLUTION n
AGENDA ITEM #
DATE: APRIL 9, 2007
DEPARTMENT: PUBLIC WORKS
DIRECTOR — DANIEL E. CENTA, P.E.
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$659,741.00 TO T.L. PRINTZ CONSTRUCTORS AND SETTING FORTH $70,259.00 FOR
CONTINGENCIES AND ADDITIONAL WORK FOR PROJECT NO. 07 -014 FY 2007 ADA
ACCESSIBILITY IMPROVEMENTS EL CENTRO DEL QUINTO SOL RECREATION
CENTER AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
ISSUE
Should City Council award a construction contract for the PROJECT NO. 07 -014 (CP0504) FY
2007 ADA ACCESSIBILITY IMPROVEMENTS EL CENTRO DEL QUINTO SOL
RECREATION CENTER to T.L. PRINTZ CONSTRUCTORS for $659,741.00.
RECOMMENDATION
Approval of this Resolution
BACKGROUND
This project will provide for the removal of the west addition, except the foundation, and the
construction of a new addition that houses an elevator and stair tower. This project will also
provide other interior renovations and upgrades, as well as site improvements to make the
facility ADA compliant in accordance with the Settlement Agreement with the Department of
Justice. This contract award is for the "Base Bid" and for Bid Add Alternate Nos. 1, 6, and 8. If
funds are remaining after the above work is completed, then we will considered adding other bid
alternates to the contract through a change order(s).
FINANCIAL IMPACT
Funds for said project will come from several sources as follows:
CP0504 - $559,670.52 (remaining in account previously appropriated)
CP0504 - $200,000.00 (EIAF Grant Contract #5373
Total = $759,670.52
Attached is a bid summary showing the result of competitive bids on this project.