HomeMy WebLinkAbout10516RESOLUTION NO. 10516
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF $61,226.75
TO DOUG VAUGHN CONCRETE, L.L.C. AND SETTING FORTH $9,184.00 FOR
CONTINGENCIES, FOR THE PROJECT NO. 05 -066 (CDO511) FY 2005 BEULAH AVE.
SIDEWALK -PHASE 2 (CDBG) PROJECT AND AUTHORIZING THE PURCHASING AGENT TO
EXECUTE THE SAME
WHEREAS, proposals for the PROJECT NO. 05 -066 (CDO511) FY 2005 BEULAH AVE.
SIDEWALK -PHASE 2 (CDBG) PROJECT have been received and examined, and;
WHEREAS, the proposal of DOUG VAUGHN CONCRETE, L.L.C. of Pueblo, Colorado was
the lowest of those bids determined to be responsible;
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract for the PROJECT NO. 05 -066 (CD0511) FY 2005 BEULAH AVE. SIDEWALK -
PHASE 2 (CDBG) PROJECT be, and the same is hereby awarded to said bidder in the amount of
$61,226.75.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo, A
Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount as
stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work .... $9,184.00
SECTION 4.
Funds for said project shall be from Project Codes CD0511
APP
PRES1DENT 9F CITY CPYWIL
INTRODUCED September 26, 2005
BY Michael Occhiato
Councilperson
D � D D
Background Paper for Proposed
RESOLUTION
4 ,60. 6 /05/(,,
AGENDA ITEM #
DATE: September 26, 2005
DEPARTMENT: PUBLIC WORKS, Daniel E Centa, P.E.
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT OF $61,226.75
TO DOUG VAUGHN CONCRETE, L.L.C. AND SETTING FORTH $9,184.00 FOR
CONTINGENCIES, FOR THE PROJECT NO. 05 -066 (CD0511) FY 2005 BEULAH AVE.
SIDEWALK -PHASE 2 (CDBG) PROJECT AND AUTHORIZING THE PURCHASING AGENT TO
EXECUTE THE SAME
ISSUE
Should City Council award a construction contract for the PROJECT NO. 05 -066 (CD0511) FY
2005 BEULAH AVE. SIDEWALK -PHASE 2 (CDBG) PROJECT to DOUG VAUGHN
CONCRETE, L.L.C. for $61,226.75.
RECOMMENDATION
Approval of this Resolution
BACKGROUND
This project will consist of the installation of new concrete sidewalk, the replacement of
damaged sidewalk and the construction of ADA curb ramps at street corners in the 700 and 800
blocks of Beulah Ave. and the 1900 and 2000 blocks of Arroyo Ave. See attached exhibits for
sidewalk locations. This project was funded for $50,000.00
FINANCIAL IMPACT
Funds for this project will be paid from Community Development Block Grant Funds, Project
Code CD0511.
Attached is a bid summary showing the result of competitive bids on this project.