HomeMy WebLinkAbout10304RESOLUTION NO. 10304
A RESOLUTION APPROVING A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$216,653.61 TO JA CONCRETE, INC., AND SETTING FORTH $23,646.00 FOR
CONTINGENCIES, FOR THE FY 2004 BRADFORD AREA SIDEWALK PROJECT AND
AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
WHEREAS, proposals for the FY 2004 BRADFORD AREA SIDEWALK PROJECT have
been received and examined, and;
WHEREAS, the proposal of JA CONCRETE, INC., of Pueblo, Colorado was the lowest of
those bids determined to be responsible;
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, that:
SECTION 1.
A contract for the FY 2004 BRADFORD AREA SIDEWALK PROJECT be, and the same is
hereby awarded to said bidder in the amount of $216,653.61.
SECTION 2.
The Purchasing Agent is hereby authorized to execute said contract on behalf of Pueblo, A
Municipal Corporation, and the City Clerk shall affix the seal of the City thereto and attest the
same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount as
stipulated in this section is hereby established for contingencies and additional work.
SECTION 4.
Contingencies and Additional Work .......$23,646.00
Funds for said project shall be from Community Development Block Grant Funds, CD0404
and CD0416.
INTRODUCED January 10, 2005
BY Michael Occhiato
Councilperson
APPROVED:
ATTESTED BY:
CITY CLERK
Background Paper for Proposed
RESOLUTION
AGENDA ITEM # 3
DATE: JANUARY 10, 2005
DEPARTMENT: PUBLIC WORKS
DIRECTOR — DANIEL E. CENTA, P.E.
TITLE
A RESOLUTION AWARDING A CONSTRUCTION CONTRACT IN THE AMOUNT
OF $216,653.61 TO JA CONCRETE, INC., AND SETTING FORTH $23,646.00 FOR
CONTINGENCIES, FOR THE FY 2004 BRADFORD AREA SIDEWALK PROJECT
AND AUTHORIZING THE PURCHASING AGENT TO EXECUTE THE SAME
ISSUE
Should City Council award a construction contract for FY 2004 BRADFORD AREA
SIDEWALK PROJECT to JA CONCRETE, INC., for $216,653.61.
RECOMMENDATION
Approval of this Resolution.
BACKGROUND
This project will construct sidewalk and curb ramps in the Bradford Area located in the
vicinity of Bradford Park, Bradford School and nearby streets.
FINANCIAL IMPACT
Funding for this project will be paid from Community Development Block Grant Funds,
Account Nos. CDO0404 and CD0416.
Attached is a bid summary showing the results of competitive bids on this project.