WHEREAS, proposals for the Historic Arkansas Riverwalk Project, Phase II, have been
received and examined; and
WHEREAS, the proposal of H.W. Houston Construction Company of Pueblo, Colorado,
was the lowest of those bids determined to be responsible; now therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, COLORADO, that:
SECTION 1.
A contract for the Historic Arkansas Riverwalk Project, Phase II, be and the same is
hereby awarded to said bidder in the amount of $2,978,806.50. The awarding of the contract for
the project set forth herein shall be subject to the filing of sufficient sureties to be approved by
the Purchasing Agent of said City, and proper execution of all contract documents.
SECTION 2.
The Purchasing Agent be, and he is hereby authorized to execute said contract on behalf
of Pueblo, a Municipal Corporation, and the City Clerk shall affix the seal of the City thereto
and attest the same.
SECTION 3.
In addition to the amount of the bid set forth, as aforementioned, an additional amount as
stipulated in this section is hereby established for contingencies and additional work.
Contingencies and Additional Work - - - - $149,000.00
SECTION 4.
Funds for said project shall be paid from Account Number 037 - 1998 - 100 - 000 - 040 -8829.
INTRODUCED July 27 . 1998
By Corinne Koehler
Councilperson
APPROVED:
i
D
President o he City Council
ATTEST:
City Clerk
•
I I
Council Agenda
TITLE : Resolution Awarding a Construction Contract for the AGENDA ITEM #
Historic Arkansas Riverwalk Project, Phase II, and
Authorizing the Purchasing Agent to Execute the Same
DEPARTMENT: PUBLIC WORKS
ISSUE
DATE: July 27, 1998
Should the City Council award a construction contract for the construction of the Historic Arkansas
Riverwalk Project, Phase 11 to H.W. Houston Construction Co. of Pueblo, Colorado, in the amount of
$2,978,806.50.
RECOMMENDATION
Approval of this Resolution
BACKGROUND
This phase of the HARP Project will include the following features:
- Sidewalks and bicycle paths along the south side of the channel and around Lake Elizabeth
- Irrigation systems
- Landscaping (south side)
- Historic riverstone wall
- Decorative lighting (south side)
- Pedestrian bridge over the channel
- Farley /Reilly water feature
- Kelly /Jackson falls at Victoria Street
- Victoria Street Plaza
- Natural area - Environmental Education facilities
- Gazebo /Event structure
Bids for this project were solicited from pre - qualified general contractors. Only one bid was
submitted, that from H.W. Houston Construction Co., of Pueblo, Colorado. Upon examination of the
bid by the Engineer, it was found to be a responsible bid. The Committee of Awards, consisting of
the City Manager, the Director of Public Works and the HARP coordinator therefore recommends that
the bid be awarded to H.W. Construction Co..
A tabulation of the contractor's bid is attached.
In addition to the contract amount of $2,978,806.00, the City will have to spend approximately
$143,000.00 for lighting fixtures which are not in the contract, and reserve approximately
$149,000.00, or 5% of the construction amount, for unforseen contingencies.
Funds to pay for this project will come from the HARP Bond proceeds (approximately $1,324,848.00
available), Grants ($1,175,00.00) and HARP Foundation commitment of approximately $986,000.00.
A spread sheet showing available funds and estimated expenditures through the nine (9) month
project is attached. It should be noted that the City may be required to provide interim financing at
the end of the project until HARP Foundation commitments are realized.
P �= -low
HARP PHASE II "A" FUNDS AND EXPENDITURES
$383,000 FOUNDATION OWES
$215,142 BAL FOR PHASE II "B"
* INCLUDES $143,000 FOR PURCHASE OF LIGHTING FIXURES BY CITY.
INCLUDES $149,000 CONTINGENCIES.
TOTAL AVAIL
SEPT
OCT
NOV
DEC
JAN
FEB
MAR
APR
MAY
BOND FUNDS
$ 1,324,848
$1,324,848
GRANTS RECD
$ 1,175,000
$ 500,000
$ 175,000
$ 500,000
FOUNDATION
986,000
$ 603,000
208,000 Due 1999
75,000 Due 2000
50,000 Due 2001
50,000 Due 2002
TOTAL
$1,324,848
$1,146,148
$907,948
$1,107,048
$ 974,248
$ 553,448
$ 606,698
$249,1481$100,248
CONSTRUCTION
SPEND PLAN
$ 178,7001$
238,300
$440,900
$ 595,800
$ 595,800
$ 446,800
$ 357,500
$148,900
**
$268,106
BALANCE
$1,146,148
$ 907,948
$467,048
$ 474,278
$ 378,448
$ 106,648
$ 249,148
$100,248
167,858 �l
$383,000 FOUNDATION OWES
$215,142 BAL FOR PHASE II "B"
* INCLUDES $143,000 FOR PURCHASE OF LIGHTING FIXURES BY CITY.