HomeMy WebLinkAbout7775RESOLUTION NO. 7775
A RESOLUTION APPROVING AMENDMENT NO. EIGHT TO CONTRACT DATED
FEBRUARY 24, 1992, BETWEEN THE CITY OF PUEBLO, A MUNICIPAL
CORPORATION, AND ISBILL ASSOCIATES, INC., RELATING TO PASSENGER
FACILITY CHARGES (PFC) AT THE PUEBLO MEMORIAL AIRPORT, AND
AUTHORIZING THE PRESIDENT OF THE CITY COUNCIL TO EXECUTE SAME
WHEREAS, the City of Pueblo, A Municipal Corporation, and Isbill Associates, Inc.
entered into a Contract on February 24, 1992, and
WHEREAS, both parties wish to amend the Contract to include fees for engineering
services relating to improvements at the Pueblo Memorial Airport,
BE IT RESOLVED BY THE CITY COUNCIL OF PUEBLO, COLORADO THAT:
SECTION 1
A certain Amendment No. Eight to the Contract, a copy of which is attached hereto and made
part thereof by reference, after having been approved as to form by the City Attorney, by and
between the City of Pueblo, a Municipal Corporation, and Isbill Associates, Inc., relating to the
inclusion of fees for engineering services to prepare and submit an Amendment to the Existing
Passenger Facility Charge (PFC) application and prepare and submit a new PFC Application for
the Pueblo Memorial Airport, is hereby approved, subject to the conditions as set forth in said
contract.
SECTION 2
Funds for said engineering services for this project shall be paid from account no. 50 -1995-
050- 000 - 040 -0020.
SECTION 3
The President of the City Council is hereby authorized to execute said Amendment No. Eight
to the Contract on behalf of Pueblo, A Municipal Corporation, and the City Clerk shall affix the
Seal of the City thereto and attest the same.
INTRODUCED December 11, 1995
BY John Califano
Councilperson
ATTEST: APPROVED:
G�
C' y Clerk President of City Council
IAI No. PUB 1806
AMENDMENT NO. EIGHT TO CONTRACT
DATED FEBRUARY 24, 1992 BETWEEN
ISBILL ASSOCIATES, INC.
AND
THE CITY OF PUEBLO, COLORADO
The Sponsor and the Engineer agree to amend their contract dated February 24, 1992, for
improvements to the Pueblo Memorial Airport, Pueblo, Colorado to include fees for engineering
services. The Improvement items covered by this amendment are described as follows:
1. Prepare and submit an Amendment to the Existing Passenger Facility Charge
(PFC) Application and prepare and submit a New PFC Application.
The Sponsor agrees to pay the Engineer for the services listed under Article II of the original
contract in the following manner:
PART A - BASIC SERVICES
Not applicable for this amendment.
BIDDING AND CONSTRUCTION ADMINISTRATION
Not applicable for this amendment.
PART B - SPECIAL SERVICES (PREPARE PFC APPLICATION)
The estimated maximum Special Services engineering costs are as follows:
Prepare and submit PFC application (Leibowitz AMC, Inc.) $12,500.00
Engineering support to Leibowitz AMC, Inc. (IAI) $4,500.00
A proposed scope of work and PFC Implementation Schedule is attached to and made
a part of this contract amendment.
Method of payment shall be as follows:
Interim payments up to 90 percent based on work performed by the Engineer and
detailed in a report submitted to the Sponsor with the request for payment. The
remaining ten percent to be paid upon approval of the PFC application by the FAA.
FIELD ENGINEERING
The estimated maximum for FIELD ENGINEERING is:
Not applicable for this amendment.
All other terms and conditions of the original contract shall remain in effect.
Page 1 of 2
IN WITNESS WHEREOF, the parties hereto have affixed their signatures this
1 I day of Dec.Eme, �--R 19 95
SPONSOR:
CITY OF PUEBLO
PUEBLO, COLORADO
l
By
President, City Council
Attest
ENGINEER:
ISBILL ASSOCIATES, INC.
j
4
Y
President
Page 2 of 2
A ISBILL
10190 EAST MONTVIEW BLVD.
(303) 364 -2500
October 2, 1995
Mr. James P. Elwood, A.A.E.
Director of Aviation
Pueblo Memorial Airport
31201 Bryan Circle
Pueblo, Colorado 81001
ASSOCIATES, INC.
• AURORA, COLORADO 60010 -2231
• FAX (303) 364 -0257
Subject: Pueblo Memorial Airport
Pueblo, Colorado
Proposal for Planning Services
Dear Mr. Elwood:
Isbill Associates, Inc. is pleased to submit this proposal to provide planning services for the
Pueblo Memorial Airport. Based on your request, we have prepared a scope of work that will
provide you with an amendment to your existing Passenger Facility Charge (PFC) Application
and a new PFC Application #2. The scope of work for these services includes the following
tasks:
Task I Schedule and Implementation Strategy
A schedule for the preparation, submittal and approval of an amended PFC Application and a
new PFC Application will be developed and submitted to the Pueblo Memorial Airport Staff and
City Council for review and approval. An implementation strategy will also be developed and
presented to the Pueblo Memorial Airport Staff and City Council for discussion and adoption.
Task 2 Determine Capital Improvement Projects
The airport's possible PFC eligible projects will be identified and cost estimates for those
projects will be developed or revised as necessary. The airport's Capital Improvement Plan will
be revised or updated as necessary.
Task 3 Airline Notice
Letters will be prepared and sent to the airlines serving the Pueblo Memorial Airport notifying
them of the City's intent to amend the existing PFC Application and prepare and submit a new
PFC Application #2. PFC start dates, end dates, and revenue projections will be calculated and
included in the Airline Notice letters.
AIRPORT CONSULTANTS • ENGINEERS
AN EQUAL OPPORTUNITY EMPLOYER
Mr. Jim P. Elwood, A.A.E.
October 2, 1995
Page 2
Task 4 Financial Plan
This task will develop a revised financing plan that incorporates potential PFC proceeds with the
airport's other funding sources. This task provides a revised financing strategy for
implementation of the airport's CIP for projects to be financed with PFC revenue.
Task 5 City Resolution
The consultant will draft a revised resolution for the City Council to adopt. The revised
resolution will identify the new projects to be financed with PFC revenue.
Task 6 Public Hearing
The consultant will attend a Public Hearing to be held in conjunction with a City Council
meeting. During the Public Hearing, the consultant will answer questions regarding the PFC
application process and the requirements of Federal Aviation Administration 14 CFR Part 158,
Passenger Facility Charges; Final Rule.
Task 7 Airline Consultation Meeting
An airline consultation meeting will be held where the amendment to the existing PFC
Application and the new projects to be financed with PFC revenue will be identified and
discussed. Project descriptions, justification, and financial plans will be reviewed with airline
representatives. The airline representatives will be provided with an Airport Layout Plan (ALP)
drawing that identifies the specific projects and their location on the airport. The consultant will
respond to all airline questions regarding the proposed amendment and new PFC Application.
Task 8 Prepare and Submit PFC Application
The consultant will prepare and submit an amended PFC Application and PFC Application #2
to the FAA, Denver Airports District Office. The PFC Applications will be submitted in the
format prescribed by the FAA.
Mr. James P. Elwood
October 2, 1995
Page 3
Task 9 Coordinate PFC Application
The FAA, Denver Airports District Office has thirty (30) days to determine if the amendment
and new application is substantially complete. The consultant will coordinate with the FAA
during this time to ensure that the applications are found to be substantially complete and
submitted for public comment and final approval .
Task 10 PFC Approval Letter
Following approval of the amended and new PFC Applications, the consultant will prepare
letters notifying the airlines serving the Pueblo Memorial Airport of the approval of the
amendment to the existing PFC Application, the total amount of PFC revenue to be collected,
and the new date the existing PFC will expire. Letters will also be prepared to submit to the
airlines serving the airport that describes PFC Application #2.
Task 11 Travel, Per Diem and Reimbursable Expenses
This task provides for consultant travel and per diem required from completion of the planning
services. Airfare will be between Denver and Pueblo, Colorado and will be billed at actual cost,
if required. Per diem will be billed at actual costs for hotel and auto rental. Out -of -town meals
will be billed at $26.00 per day: or $6.00 for breakfast, $8.00 for lunch and $12.00 for dinner.
All other expenses will be billed at actual cost.
Task M.1 Airfare DEN -PUB
It is anticipated that two (2) trips will be required by Isbill Associates, Inc. and three (3) trips
by Leibowitz AMC, Inc. to complete the amended PFC Application and PFC Application #2.
Trips will be scheduled for a presentation to the City Council of the PFC projects and
implementation strategy, Public Hearing, and Airline Consultation meeting.
Task 11.2 Per Diem Days
It is anticipated that three (3) per diem days in Pueblo, Colorado will be required by Isbill
Associates, Inc. and Leibowitz AMC, Inc. to complete the amended PFC Application and PFC
Application #2.
Mr. James P. Elwood
October 2, 1995
Page 4
Project Cost and Schedule
All financial and legal tasks described by this scope of work will be completed by Leibowitz
Airport Management Consultants (AMC), Inc., a DBE firm that specializes in financial
consulting to airports. All other tasks will be completed by Isbill Associates, Inc. Our fee for
to perform the planning services described above will be a lump sum of $17,000.00. Fees for
preparation of the amendment to the existing PFC Application, PFC Application #2, and your
original PFC Application will be included as an administrative cost in PFC Application #2 and
reimbursed by PFC revenue.
We estimate that it will take approximately sixty -five (65) days to amend the existing
application, prepare PFC Application #2 and submit them to the FAA. Assuming we receive
your approval and notice -to- proceed by October 10, 1995 we would expect to submit the
amendment and new application by December 15, 1995. A "draft" PFC Implementation
Schedule is attached for your review and information. As always, we truly appreciate the
opportunity to be of service to the Pueblo Memorial Airport.
Very truly yours,
Isbill Ass 'at , Inc.
.G. Isbill
President
HGI \evt
PUEBLO, COLORADO
Preliminary
PFC /mplomontatlon Schedule
DATE ACTIVITY
1012 Start Project, review PFC requirements
10110 Review amendment and new application notice drafts and final
determination of new projects
10/11 Official Notices to Airlines (Amendment and New Application)
10/20 If City Attorney determines neccessary, notice of public hearing
11/13 New Resolution approved by City Council, (public hearing if
necoessary )
11113 Aldine Consultation meetings - 10:30am
12/12 Airline Certification of Agreement/Disagreement
(Amendment and New Application)
12/15 Submit New PFC Application and amendment to FAA
1/15 FAA Certification of Substantially Complete for new application
and amendment approval
4/15 FAA approval of new PFC application
4/25 Notify Airlines of New Application and amendment approval